Question 390
During a fictional public-service network-security incident, the only PLC image backup is on an unverified USB drive beside the engineering workstation. Which underlying security mechanism best explains the observed situation?
Explanation
Correct Answer
Recovery readiness requires tested integrity, version compatibility and controlled custody of critical configurations. The only PLC image backup is on an unverified USB drive beside the engineering workstation. Maintain protected backups and exercise recovery on representative lab or spare hardware.
Incorrect Answers
Cyber integrity can be compromised through local access and physical configuration manipulation. This evaluates physical tampering indicators, whereas the only PLC image backup is on an unverified USB drive beside the engineering workstation.
An approach centered on security level target reasoning answers a different question. Security level targets must follow risk-informed threat capability, impact and zone characteristics. In contrast, the only PLC image backup is on an unverified USB drive beside the engineering workstation.
OT vulnerability prioritization must combine exploitability with process consequence and reachable pathways. That could matter for weakness severity in safety context; it does not settle the problem that the only PLC image backup is on an unverified USB drive beside the engineering workstation.