Question 430
At Harbor Public Services, an architecture review of citizen application delivery across government offices and regional shared services is underway during a scheduled network modernization (DES-1-07-2). The review is led by the municipal infrastructure group. The documented design gap: an architect compares owned MPLS access and managed internet under one-time installation cost alone. The solution must proceed with a reversible and accountable decision path. Which architectural principle best explains the observed design trade-off?
Explanation
Correct Answer
The governing architecture rule is: Lifecycle decisions need comparable CAPEX and OPEX over the design horizon. The specific case condition is: an architect compares owned MPLS access and managed internet under one-time installation cost alone. This supports the design response: Model recurring carrier fees support labor lifecycle replacement and capital investment across the same period. Confirm the conclusion using the case-specific evidence: The total-cost comparison exposes recurring operations and refresh assumptions for both architectures.
Incorrect Answers
Recovery point objectives govern replica consistency and transfer frequency rather than circuit speed alone. That principle governs the offered alternative, but the facts in this question are explained by: Lifecycle decisions need comparable CAPEX and OPEX over the design horizon. The two technical dependencies must be distinguished.
The alternate statement is relevant when recovery time objectives measure end-to-end service restoration not only link reconvergence. Here the root condition follows: Lifecycle decisions need comparable CAPEX and OPEX over the design horizon. It is not the same causal explanation.
The offered principle concerns: Fixed sequential dependencies require explicit readiness gates regardless of agile tooling. That is not what the current scenario establishes. Its controlling mechanism is: Lifecycle decisions need comparable CAPEX and OPEX over the design horizon.