Question 160
A remote wildfire-response program deploys teams without planning relief staffing for prolonged shifts. The team has identified a response and must obtain a justified decision before moving forward. Which next decision BEST preserves the agreed business outcome?
Explanation
Correct Answer
This decision respects the accountable project authority and the scenario’s remaining exposure: Have safety leadership approve surge capacity and fallback arrangements. The response being governed is Resource the rota with fatigue limits, backup personnel, and safe escalation coverage. and the completion measure is Drills show continuous qualified coverage without violating safe working-hour constraints.
Incorrect Answers
Raise the unresolved prioritization decision to the portfolio owner rather than instruct both teams to accelerate. That safeguard does not address the specific risk here: headcount alone does not establish sustainable response capacity. The relevant follow-up is: Have safety leadership approve surge capacity and fallback arrangements.
Protect mandatory accessibility acceptance even if a feature release must move. That safeguard does not address the specific risk here: headcount alone does not establish sustainable response capacity. The relevant follow-up is: Have safety leadership approve surge capacity and fallback arrangements.
Request sponsor confirmation of post-project benefit responsibilities before closure approval. That safeguard does not address the specific risk here: headcount alone does not establish sustainable response capacity. The relevant follow-up is: Have safety leadership approve surge capacity and fallback arrangements.