Question 560
At fictional Sparrow Research, the network architecture group is preparing a proposal for innovation campus during the business change review (case HPE7A11-1.3-035). The review identified this issue: a call center states that all phones must work during uplink failure but specifies no maximum call loss. Which recurring control most directly reduces the likelihood of this design problem returning?
Explanation
Correct Answer
This recurring control is targeted to the risk that A call center states that all phones must work during uplink failure but specifies no maximum call loss. The preventative action is to reconfirm failure targets with the telephony service owner. The underlying design correction remains to derive quantified failover and call-recovery objectives for voice services.
Incorrect Answers
This option — “Compare segmentation outcomes against the stakeholder policy matrix” — checks interpret technical requirements, not whether the design resolves the stated fault: a call center states that all phones must work during uplink failure but specifies no maximum call loss. The selected direct criterion is “Reconfirm failure targets with the telephony service owner.”.
“Reconfirm cutover permissions before each plant wave” is a test of interpret technical requirements. That does not establish “Reconfirm failure targets with the telephony service owner.” for the reported issue (a call center states that all phones must work during uplink failure but specifies no maximum call loss).
The offered evidence “Audit management access settings after onboarding new devices” relates to interpret technical requirements. The actual question describes this issue: a call center states that all phones must work during uplink failure but specifies no maximum call loss. The corresponding response is “Reconfirm failure targets with the telephony service owner.”.