Question 90
In a separate simulated transport environment, a short-term cellular link remains active after a field commissioning visit ends. Which validation is needed before this change is approved?
Explanation
Correct Answer
Confirm the safe support fallback before disabling a connection needed for an active incident. In a separate transport environment, a short-term cellular link remains active after a field commissioning visit ends.
Incorrect Answers
Confirm vendor scan restrictions, throughput limits, maintenance windows and recovery procedures before probing. This evaluates passive inventory discovery, whereas in a separate transport environment, a short-term cellular link remains active after a field commissioning visit ends.
An approach centered on safety-function dependencies answers a different question. Do not assume a cybersecurity test may actuate safety equipment or bypass protective functions. In contrast, in a separate transport environment, a short-term cellular link remains active after a field commissioning visit ends.
Confirm decision rights and change-control escalation before assigning mitigation owners. That could matter for cross-functional workshop participation; it does not settle the problem that in a separate transport environment, a short-term cellular link remains active after a field commissioning visit ends.