Question 110
During a fictional manufacturing network-security incident, procurement signs a network contract before the cybersecurity team can influence IACS zoning. Which validation is needed before this change is approved?
Explanation
Correct Answer
Define decision makers and contractual design-change authority before revising supplier specifications. Procurement signs a network contract before the cybersecurity team can influence IACS zoning.
Incorrect Answers
Obtain read-only evidence under change control before using unverified diagrams for interventions. That could matter for architecture drawing provenance; it does not settle the problem that procurement signs a network contract before the cybersecurity team can influence IACS zoning.
The proposed step addresses historian data-flow context: Capture operational latency and data-integrity constraints before testing historian permissions. The issue here is procurement signs a network contract before the cybersecurity team can influence IACS zoning.
This alternative relates to maintenance-window availability: Obtain production, safety and vendor authorization before live controller interrogation or reboot. The present difficulty is that procurement signs a network contract before the cybersecurity team can influence IACS zoning.