Question 690
At fictional Cedar Financial, the quality team is reviewing a change to its customer account application. A team approves a candidate based on results from the previous build, but the release artifact was rebuilt afterwards. Which observed result would best demonstrate that the intended improvement worked?
Explanation
Correct Answer
The relevant evidence confirms that the team can link results to the exact immutable artifact being considered for release. The critical link is that test evidence is reliable only when connected to the exact configuration tested.
Incorrect Answers
Impacted cases are revised or consciously retained with justification; that concerns traceability of change. That result can occur without proving the requested improvement; in this case, the required evidence is that the deployed candidate hash matches the build covered by the accepted test results.
The agreed estimate reflects previously overlooked fixture and environment tasks; that concerns planning poker. That result can occur without proving the requested improvement; in this case, the required evidence is that the deployed candidate hash matches the build covered by the accepted test results.
The defect decision cites an agreed requirement or updated acceptance criterion; that concerns defect triage disagreement. That result can occur without proving the requested improvement; in this case, the required evidence is that the deployed candidate hash matches the build covered by the accepted test results.