Question 440
A new provisioned model deployment fails creation because the requested capacity is below its minimum PTU size. The team is preparing a controlled change and wants evidence that it corrects the root cause. For acceptance, the reviewer must confirm that the eligible PTU configuration creates successfully. Which change most directly addresses the observed behavior?
Explanation
Correct Answer
Provisioned deployment types enforce minimum per-model capacity units. A test run should show that the eligible PTU configuration creates successfully.
Incorrect Answers
Unused quota does not guarantee physical PTU capacity at the requested time.
Quota is a prerequisite independent of model name or payment method.
PTU reservations and deployment resizing are independent cost commitments.