Question 800
A cloud analytics firm documents a two-hour RPO while scheduling its only backup every twelve hours. The architect proposes: Align backup frequency, replication and recovery monitoring with measurable RPO and RTO obligations. What test distinguishes successful risk mitigation from an unrelated improvement?
Explanation
Correct Answer
The design is: Align backup frequency, replication and recovery monitoring with measurable RPO and RTO obligations. It addresses this failure condition: An untested backup cadence cannot satisfy a recovery objective tighter than its capture interval. The strongest direct acceptance evidence is: A test failure shows no more than two hours of accepted data loss and finishes recovery inside the deadline. The evidence must show the specific proposed control works, not an unrelated improvement.
Incorrect Answers
Enterprise IT risk scoring cannot automatically represent physical-process harm from OT compromise. That finding would not establish that the current design works. The required evidence is: A test failure shows no more than two hours of accepted data loss and finishes recovery inside the deadline.
Recoverability does not eliminate confidentiality harm when attackers copy data before encryption. That finding would not establish that the current design works. The required evidence is: A test failure shows no more than two hours of accepted data loss and finishes recovery inside the deadline.
A privileged account common to production and backup collapses the intended trust boundary. That finding would not establish that the current design works. The required evidence is: A test failure shows no more than two hours of accepted data loss and finishes recovery inside the deadline.