Question 330
In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. Which continuing control would most directly reduce the chance of this problem recurring?
Explanation
Correct Answer
This ongoing practice maintains the improvement: Track SPI trends with actual schedule logic and critical work. It follows the targeted action (calculate SPI = EV / PV = 0.90 and examine the schedule recovery plan.) and provides a way to catch recurrence. The underlying principle is: An SPI below 1 signals that earned value trails scheduled value.
Incorrect Answers
“Check quality and scope completeness before celebrating favorable CPI” addresses recurrence of another problem: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. That problem depends on: This ongoing practice maintains the improvement: Check quality and scope completeness before celebrating favorable CPI. The recurring risk here is: In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. The more targeted safeguard is “Track SPI trends with actual schedule logic and critical work” because this ongoing practice maintains the improvement: Track SPI trends with actual schedule logic and critical work.
“Validate each package against the scope baseline before scheduling tasks” addresses recurrence of another problem: In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. That problem depends on: This ongoing practice maintains the improvement: Validate each package against the scope baseline before scheduling tasks. The recurring risk here is: In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. The more targeted safeguard is “Track SPI trends with actual schedule logic and critical work” because this ongoing practice maintains the improvement: Track SPI trends with actual schedule logic and critical work.
“Use consistent package definitions and control accounts for reporting” addresses recurrence of another problem: In a fictional CAPM project situation, a museum exhibit team cannot assign cost accountability because its WBS elements are too broad. That problem depends on: This ongoing practice maintains the improvement: Use consistent package definitions and control accounts for reporting. The recurring risk here is: In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. The more targeted safeguard is “Track SPI trends with actual schedule logic and critical work” because this ongoing practice maintains the improvement: Track SPI trends with actual schedule logic and critical work.