Question 560
In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: The WBS dictionary defines outputs, boundaries, and acceptance criteria. It supports the chosen response (decompose the deliverable scope into verifiable WBS work packages.) rather than merely recording activity. The principle is: A WBS organizes the full approved scope by deliverables rather than by random activities.
Incorrect Answers
“Work packages support practical estimating, tracking, and ownership” is evidence for a different source case: In a fictional CAPM project situation, a museum exhibit team cannot assign cost accountability because its WBS elements are too broad. Its related mechanism is: A usable WBS supports planning and cost control at a manageable level. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. The source-keyed acceptance evidence is “The WBS dictionary defines outputs, boundaries, and acceptance criteria”.
“Retest results meet the specified pressure threshold with defect closure evidence” is evidence for a different source case: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. Its related mechanism is: Conformance must be demonstrated against requirements, not presumed from installation. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. The source-keyed acceptance evidence is “The WBS dictionary defines outputs, boundaries, and acceptance criteria”.
“The change record aligns drawings, budget, procurement, schedule, and acceptance” is evidence for a different source case: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. Its related mechanism is: Integration management keeps plan components internally consistent. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a highway resurfacing project lists asphalt and drainage as tasks but misses acceptance deliverables. The source-keyed acceptance evidence is “The WBS dictionary defines outputs, boundaries, and acceptance criteria”.