Question 670
In a fictional CAPM project situation, a pipeline design has task A 2d then B 9d or C 6d, followed by D 3d; a manager assumes the shorter branch controls. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: The longest path of dependencies, not shortest, determines minimum project duration. Consequently, the targeted action is: Identify A-B-D as the 14-day controlling path and test the finish date against it. This reasoning can be checked against: The network has A-B-D 14 days versus A-C-D 11 days.
Incorrect Answers
“The longest dependent path sets the earliest possible finish when resources are unconstrained” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a library renewal schedule has two paths: A 4d then B 6d; A 4d then C 3d; both precede D 2d. There the technical reason is: The longest dependent path sets the earliest possible finish when resources are unconstrained. In this question, the reported issue is: In a fictional CAPM project situation, a pipeline design has task A 2d then B 9d or C 6d, followed by D 3d; a manager assumes the shorter branch controls. The controlling principle is instead: The longest path of dependencies, not shortest, determines minimum project duration.
“Critical path duration follows the longest start-to-finish dependent sequence” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a port upgrade has branch X 5d plus Y 4d and branch X 5d plus Z 7d, joining at final acceptance T 2d. There the technical reason is: Critical path duration follows the longest start-to-finish dependent sequence. In this question, the reported issue is: In a fictional CAPM project situation, a pipeline design has task A 2d then B 9d or C 6d, followed by D 3d; a manager assumes the shorter branch controls. The controlling principle is instead: The longest path of dependencies, not shortest, determines minimum project duration.
“Earned value below planned value indicates less budgeted work achieved than scheduled” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. There the technical reason is: Earned value below planned value indicates less budgeted work achieved than scheduled. In this question, the reported issue is: In a fictional CAPM project situation, a pipeline design has task A 2d then B 9d or C 6d, followed by D 3d; a manager assumes the shorter branch controls. The controlling principle is instead: The longest path of dependencies, not shortest, determines minimum project duration.