Question 300
A government grant project finished outputs on time but the recipient organization has not begun tracking promised community benefits. The team has identified a response and must obtain a justified decision before moving forward. Which accountable follow-through decision BEST protects project value?
Explanation
Correct Answer
This decision respects the accountable project authority and the scenario’s remaining exposure: Request sponsor confirmation of post-project benefit responsibilities before closure approval. The response being governed is Transition benefit metrics and ownership to the receiving organization with an agreed measurement cadence. and the completion measure is Approved handover includes accountable outcome owners and scheduled benefit reviews.
Incorrect Answers
Document which components can adapt and which require controlled compliance baselines. That safeguard does not address the specific risk here: closing solely on installed assets leaves the grant's promised public value unmeasured. The relevant follow-up is: Request sponsor confirmation of post-project benefit responsibilities before closure approval.
Close the original charter through governance while funding successor discovery separately. That safeguard does not address the specific risk here: closing solely on installed assets leaves the grant's promised public value unmeasured. The relevant follow-up is: Request sponsor confirmation of post-project benefit responsibilities before closure approval.
Clinical governance must approve deployment thresholds and human escalation boundaries. That safeguard does not address the specific risk here: closing solely on installed assets leaves the grant's promised public value unmeasured. The relevant follow-up is: Request sponsor confirmation of post-project benefit responsibilities before closure approval.