Question 120
A digital health programme publishes a monthly status PDF but clinicians need weekly safety updates while regulators need documented milestone evidence. What repeating management check should be included in the project controls?
Explanation
Correct Answer
Periodically check communication effectiveness and update channels when stakeholder availability, information needs or project risks change. It is appropriate because useful communication is two-way and audience-specific; sending more documents does not ensure that recipients understand or act on relevant information. The recurring failure risk is illustrated by: A digital health programme publishes a monthly status PDF but clinicians need weekly safety updates while regulators need documented milestone evidence.
Incorrect Answers
This repeating check is mainly concerned with lead a frightened delivery team through change, not with the recurring weakness described here: A digital health programme publishes a monthly status PDF but clinicians need weekly safety updates while regulators need documented milestone evidence. The useful ongoing safeguard in this situation is to periodically check communication effectiveness and update channels when stakeholder availability, information needs or project risks change.
This repeating check is mainly concerned with map adoption impact across operational groups, not with the recurring weakness described here: A digital health programme publishes a monthly status PDF but clinicians need weekly safety updates while regulators need documented milestone evidence. The useful ongoing safeguard in this situation is to periodically check communication effectiveness and update channels when stakeholder availability, information needs or project risks change.
This repeating check is mainly concerned with resolve disagreement in a distributed project team, not with the recurring weakness described here: A digital health programme publishes a monthly status PDF but clinicians need weekly safety updates while regulators need documented milestone evidence. The useful ongoing safeguard in this situation is to periodically check communication effectiveness and update channels when stakeholder availability, information needs or project risks change.