Question 560
A municipal archive project completes its product delivery but does not reconcile actual benefits expectations, cost and lessons for the closing report. Which ongoing control would best prevent this failure from recurring?
Explanation
Correct Answer
Retain approved records and schedule post-project benefit checks instead of allowing commitments to disappear when the team disbands. It is appropriate because closure requires evidence of completion and transition, not merely cessation of project tasks; a final report informs the board and future work. The recurring failure risk is illustrated by: A municipal archive project completes its product delivery but does not reconcile actual benefits expectations, cost and lessons for the closing report.
Incorrect Answers
This repeating check is mainly concerned with separate assurance, control and acceptance, not with the recurring weakness described here: A municipal archive project completes its product delivery but does not reconcile actual benefits expectations, cost and lessons for the closing report. The useful ongoing safeguard in this situation is to retain approved records and schedule post-project benefit checks instead of allowing commitments to disappear when the team disbands.
This repeating check is mainly concerned with resolve failed quality criteria before acceptance, not with the recurring weakness described here: A municipal archive project completes its product delivery but does not reconcile actual benefits expectations, cost and lessons for the closing report. The useful ongoing safeguard in this situation is to retain approved records and schedule post-project benefit checks instead of allowing commitments to disappear when the team disbands.
This repeating check is mainly concerned with product register and configuration identification, not with the recurring weakness described here: A municipal archive project completes its product delivery but does not reconcile actual benefits expectations, cost and lessons for the closing report. The useful ongoing safeguard in this situation is to retain approved records and schedule post-project benefit checks instead of allowing commitments to disappear when the team disbands.