Question 610
A city social-services project predicts a stage-cost exception, and its manager changes objectives without consulting the board to avoid delay. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that only the authority owning the exceeded tolerance can decide a new direction; daily management delegation does not include unilateral major scope reauthorization. That reasoning makes the targeted action appropriate: obtain board direction on the exception, including whether to revise, suspend or stop work and whether an exception plan is required. The described project conditions show why the distinction matters: A city social-services project predicts a stage-cost exception, and its manager changes objectives without consulting the board to avoid delay.
Incorrect Answers
Arrange ongoing support and follow-on actions describes a different management issue. The relevant cause instead is that only the authority owning the exceeded tolerance can decide a new direction; daily management delegation does not include unilateral major scope reauthorization.
Authorize work packages describes a different management issue. The relevant cause instead is that only the authority owning the exceeded tolerance can decide a new direction; daily management delegation does not include unilateral major scope reauthorization.
Evaluate performance and lessons describes a different management issue. The relevant cause instead is that only the authority owning the exceeded tolerance can decide a new direction; daily management delegation does not include unilateral major scope reauthorization.