Question 280
Fictional Fernhaven Logistics runs the contract processing workload at a primary cluster room storage site. While completing change preflight, the field handoff documents: An engineer inserts a new NVRAM assembly into an enclosure location inferred from a different FlashArray generation. The team requires a direct technical explanation and measured acceptance check. Which preventive control most directly reduces this failure risk?
Explanation
Correct Answer
The ongoing safeguard is: Include model generation and slot labels in the step-by-step hardware runbook. The recurring exposure to avoid is: The target slot selection has not been validated for the shipped model and upgrade kit. A continuing effectiveness check is: Inventory detects the correct NVRAM module in its published position after installation.
Incorrect Answers
This alternative concerns: Brief the crew on ESD and lifting requirements before unpacking hardware. It is associated with electrostatic and lifting procedures, rather than the question’s determining condition. The case instead turns on: The target slot selection has not been validated for the shipped model and upgrade kit. The more directly applicable prevention choice is: Include model generation and slot labels in the step-by-step hardware runbook.
The offered choice addresses: Record licensing prerequisites beside each requested service in the implementation plan. That concerns service entitlement and provisioning readiness, rather than the specific failure described here. The deciding issue in this scenario is: The target slot selection has not been validated for the shipped model and upgrade kit. The more directly applicable prevention choice is: Include model generation and slot labels in the step-by-step hardware runbook.
This option focuses on: Include blanking and cable airflow inspection in physical installation signoff. That can be relevant to rack blanking and airflow paths, but it does not establish the required case-specific result. The current case instead identifies: The target slot selection has not been validated for the shipped model and upgrade kit. The more directly applicable prevention choice is: Include model generation and slot labels in the step-by-step hardware runbook.