Question 670
At the Riverton university operations unit, teams assume every change must be approved by the same committee even when risks vary greatly. Which interpretation best explains the service-management issue?
Explanation
Correct Answer
A change authority is the person or group authorized to decide whether a change proceeds. This explains why the team at the Riverton university operations unit should assign suitable change authorities by change type and risk, rather than focus on an unrelated service issue.
Incorrect Answers
Service level agreements balance stakeholder expectations with feasible service delivery. That describes the separate concern of service level management: negotiate targets, not the evidence presented here at the Riverton university operations unit. The decisive distinction is that a change authority is the person or group authorized to decide whether a change proceeds.
Metrics should help evaluate the service outcome rather than encourage meaningless green dashboards. That describes the separate concern of service level management: meaningful measures, not the evidence presented here at the Riverton university operations unit. The decisive distinction is that a change authority is the person or group authorized to decide whether a change proceeds.
Planning improvement turns the desired state into feasible work. That describes the separate concern of continual improvement: improvement plan, not the evidence presented here at the Riverton university operations unit. The decisive distinction is that a change authority is the person or group authorized to decide whether a change proceeds.