Question 730
At the Highmere insurer, a root cause is confirmed and the permanent correction requires production configuration changes. Which interpretation best explains the service-management issue?
Explanation
Correct Answer
Problem management investigates causes; authorized changes implement controlled remediation. This explains why the team at the Highmere insurer should submit the correction through appropriate change enablement while tracking the problem, rather than focus on an unrelated service issue.
Incorrect Answers
Completion of technical deployment alone does not demonstrate a successful change. That describes the separate concern of change enablement: post-change review, not the evidence presented here at the Highmere insurer. The decisive distinction is that problem management investigates causes; authorized changes implement controlled remediation.
A workaround can reduce incident impact before the underlying cause is removed. That describes the separate concern of incident management: workaround, not the evidence presented here at the Highmere insurer. The decisive distinction is that problem management investigates causes; authorized changes implement controlled remediation.
A standard change is low risk, well understood and preauthorized; it does not need a fresh case-by-case authorization. That describes the separate concern of change enablement: standard change, not the evidence presented here at the Highmere insurer. The decisive distinction is that problem management investigates causes; authorized changes implement controlled remediation.