McAfee Secure

Exam Code: ITILFND V5

Exam Name: ITIL Foundation (Version 5)

Certification Provider: ITIL

Corresponding Certification: ITIL Foundation (Version 5)

ITIL ITILFND V5 Questions & Answers

Study with Up-To-Date REAL Exam Questions and Answers from the ACTUAL Test

78 Questions & Answers with Testing Engine

"ITIL Foundation (Version 5) Exam", also known as ITILFND V5 exam, is a ITIL certification exam.

Pass your tests with the always up-to-date ITILFND V5 Exam Engine. Your ITILFND V5 training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

ITIL ITILFND V5 Practice Test 9

Question 80

A global SaaS provider centralizes procurement without consulting local service teams or their regional partners. Which step best supports the intended result?

  1. Examine contractual resilience and alternatives through the partners-and-suppliers dimension.
  2. Clarify partner responsibilities, collaboration and contracts for shared incident resolution.
  3. Balance organizations-and-people needs with supplier relationships and local process realities.
  4. Evaluate roles, skills, accountability and capacity within the organizations-and-people dimension.

Explanation

Correct Answer

C:

This approach addresses the underlying concern: a centrally efficient supplier decision can still undermine local service delivery. A successful result would be that local teams can fulfill agreed outcomes under workable partner arrangements.

Incorrect Answers

A:

External dependencies can interrupt consumer outcomes even when internal operations work. That explains why “Examine contractual resilience and alternatives through the partners-and-suppliers dimension” is useful for its own dependency, but the present failure follows a different constraint: This approach addresses the underlying concern: a centrally efficient supplier decision can still undermine local service delivery. The targeted correction is “Balance organizations-and-people needs with supplier relationships and local process realities”.

B:

The proposed action focuses on a control governed by: This approach addresses the underlying concern: supplier boundary gaps lead to unresolved issues across an otherwise functional service. In this question the binding condition is: This approach addresses the underlying concern: a centrally efficient supplier decision can still undermine local service delivery. Applying “Balance organizations-and-people needs with supplier relationships and local process realities” addresses that specific cause instead.

D:

This option would change the part of the system described by: The proposed technology change omits human capability and organizational structure. The reported behavior instead arises because this approach addresses the underlying concern: a centrally efficient supplier decision can still undermine local service delivery. The direct remediation is “Balance organizations-and-people needs with supplier relationships and local process realities”.

Question 81

A food-delivery provider begins designing a new tracking feature before investigating what customers actually struggle to accomplish. Which approach most directly addresses the issue?

  1. Adapt the eight activities to the work and desired outcomes instead of enforcing a rigid one-time waterfall.
  2. Use the discover activity to clarify needs, opportunities and constraints before committing to a solution.
  3. Use the operate activity to maintain the live product and service under agreed operating conditions.
  4. Allow design and acquisition to inform each other iteratively as supplier capability is learned.

Explanation

Correct Answer

B:

The problem arises because the team selected a design without understanding the desired outcomes. The proposed change targets that cause; verify that validated user research identifies the problems the feature should address.

Incorrect Answers

A:

The proposed action focuses on a control governed by: This approach addresses the underlying concern: ITIL product and service lifecycle activities form a flexible, connected management model. In this question the binding condition is: The team selected a design without understanding the desired outcomes. Applying “Use the discover activity to clarify needs, opportunities and constraints before committing to a solution” addresses that specific cause instead.

C:

This option would change the part of the system described by: Sustained live performance depends on operational monitoring and control beyond deployment. The reported behavior instead arises because the team selected a design without understanding the desired outcomes. The direct remediation is “Use the discover activity to clarify needs, opportunities and constraints before committing to a solution”.

D:

Lifecycle activities are interconnected and not strictly linear stages. That explains why “Allow design and acquisition to inform each other iteratively as supplier capability is learned” is useful for its own dependency, but the present failure follows a different constraint: The team selected a design without understanding the desired outcomes. The targeted correction is “Use the discover activity to clarify needs, opportunities and constraints before committing to a solution”.

Question 82

A banking app team understands customer needs but has no clear functional model, experience flow or acceptance criteria. Which step best supports the intended result?

  1. Use acquire for the partner capability and build for integration into the firm's service.
  2. Use the acquire activity to obtain the necessary external product and service components.
  3. Use the design activity to define requirements and the intended product/service solution.
  4. Coordinate discover, design and acquire around required outcomes before implementation.

Explanation

Correct Answer

C:

The response is relevant because needs have been identified but not translated into a coherent design. It should produce a result in which stakeholders agree on a feasible design and testable requirements.

Incorrect Answers

A:

“Use acquire for the partner capability and build for integration into the firm's service” acts on a neighboring technical dependency: Obtaining a component and implementing the complete solution are related but distinct activities. It does not resolve the stated condition, whose causal mechanism is: Needs have been identified but not translated into a coherent design. The required action is “Use the design activity to define requirements and the intended product/service solution”.

B:

This option would change the part of the system described by: The requirement is to source a capability under suitable terms rather than create it from scratch. The reported behavior instead arises because needs have been identified but not translated into a coherent design. The direct remediation is “Use the design activity to define requirements and the intended product/service solution”.

D:

The proposed action focuses on a control governed by: Buying or building should follow a coherent understanding of needs and feasibility. In this question the binding condition is: Needs have been identified but not translated into a coherent design. Applying “Use the design activity to define requirements and the intended product/service solution” addresses that specific cause instead.

Question 83

A local authority needs specialist identity software that should be sourced rather than built internally. Which approach most directly addresses the issue?

  1. Use the acquire activity to obtain the necessary external product and service components.
  2. Use the design activity to define requirements and the intended product/service solution.
  3. Use acquire for the partner capability and build for integration into the firm's service.
  4. Return to discover and design and then build and transition the improvement iteratively.

Explanation

Correct Answer

A:

This intervention is directed at the cause: the requirement is to source a capability under suitable terms rather than create it from scratch. Confirm its value by checking that selected components and contracts meet agreed security and operational requirements.

Incorrect Answers

B:

Needs have been identified but not translated into a coherent design. That explains why “Use the design activity to define requirements and the intended product/service solution” is useful for its own dependency, but the present failure follows a different constraint: The requirement is to source a capability under suitable terms rather than create it from scratch. The targeted correction is “Use the acquire activity to obtain the necessary external product and service components”.

C:

The proposed action focuses on a control governed by: Obtaining a component and implementing the complete solution are related but distinct activities. In this question the binding condition is: The requirement is to source a capability under suitable terms rather than create it from scratch. Applying “Use the acquire activity to obtain the necessary external product and service components” addresses that specific cause instead.

D:

“Return to discover and design and then build and transition the improvement iteratively” acts on a neighboring technical dependency: Lifecycle activities can repeat in response to real user needs. It does not resolve the stated condition, whose causal mechanism is: The requirement is to source a capability under suitable terms rather than create it from scratch. The required action is “Use the acquire activity to obtain the necessary external product and service components”.

Question 84

A retailer has an approved shopping-cart design but no tested implementation. Which step best supports the intended result?

  1. Use the build activity to create and verify the required solution components.
  2. Use the transition activity to introduce the change safely into intended use.
  3. Link build verification with deliver fulfilment and consumer access testing.
  4. Coordinate build and transition with adoption, training and cutover preparations.

Explanation

Correct Answer

A:

This approach addresses the underlying concern: the designed capability has not yet been implemented into working product components. A successful result would be that the integrated implementation passes its defined build and test criteria.

Incorrect Answers

B:

The proposed action focuses on a control governed by: A technically tested build is not yet an operationally accepted service change. In this question the binding condition is: This approach addresses the underlying concern: the designed capability has not yet been implemented into working product components. Applying “Use the build activity to create and verify the required solution components” addresses that specific cause instead.

C:

“Link build verification with deliver fulfilment and consumer access testing” acts on a neighboring technical dependency: Technical readiness and entitlement delivery are separate success requirements. It does not resolve the stated condition, whose causal mechanism is: This approach addresses the underlying concern: the designed capability has not yet been implemented into working product components. The required action is “Use the build activity to create and verify the required solution components”.

D:

This option would change the part of the system described by: This approach addresses the underlying concern: a working implementation is not equivalent to successful entry into service. The reported behavior instead arises because this approach addresses the underlying concern: the designed capability has not yet been implemented into working product components. The direct remediation is “Use the build activity to create and verify the required solution components”.

Question 85

An enterprise has a tested software release but has not prepared environments, users or operational handover. Which approach most directly addresses the issue?

  1. Use the transition activity to introduce the change safely into intended use.
  2. Use the build activity to create and verify the required solution components.
  3. Link build verification with deliver fulfilment and consumer access testing.
  4. Use the support activity to help users and restore effective service consumption.

Explanation

Correct Answer

A:

The problem arises because a technically tested build is not yet an operationally accepted service change. The proposed change targets that cause; verify that operational teams and users can adopt the change with continuity maintained.

Incorrect Answers

B:

“Use the build activity to create and verify the required solution components” acts on a neighboring technical dependency: This approach addresses the underlying concern: the designed capability has not yet been implemented into working product components. It does not resolve the stated condition, whose causal mechanism is: A technically tested build is not yet an operationally accepted service change. The required action is “Use the transition activity to introduce the change safely into intended use”.

C:

This option would change the part of the system described by: Technical readiness and entitlement delivery are separate success requirements. The reported behavior instead arises because a technically tested build is not yet an operationally accepted service change. The direct remediation is “Use the transition activity to introduce the change safely into intended use”.

D:

This approach addresses the underlying concern: ongoing assistance and issue resolution are needed after delivery. That explains why “Use the support activity to help users and restore effective service consumption” is useful for its own dependency, but the present failure follows a different constraint: A technically tested build is not yet an operationally accepted service change. The targeted correction is “Use the transition activity to introduce the change safely into intended use”.

Question 86

A streaming service experiences degraded capacity during peak usage despite having a stable release pipeline. Which step best supports the intended result?

  1. Allow design and acquisition to inform each other iteratively as supplier capability is learned.
  2. Use the operate activity to maintain the live product and service under agreed operating conditions.
  3. Use the discover activity to clarify needs, opportunities and constraints before committing to a solution.
  4. Use acquire for the partner capability and build for integration into the firm's service.

Explanation

Correct Answer

B:

The response is relevant because sustained live performance depends on operational monitoring and control beyond deployment. It should produce a result in which capacity, availability and runtime health meet operating requirements.

Incorrect Answers

A:

“Allow design and acquisition to inform each other iteratively as supplier capability is learned” acts on a neighboring technical dependency: Lifecycle activities are interconnected and not strictly linear stages. It does not resolve the stated condition, whose causal mechanism is: Sustained live performance depends on operational monitoring and control beyond deployment. The required action is “Use the operate activity to maintain the live product and service under agreed operating conditions”.

C:

The team selected a design without understanding the desired outcomes. That explains why “Use the discover activity to clarify needs, opportunities and constraints before committing to a solution” is useful for its own dependency, but the present failure follows a different constraint: Sustained live performance depends on operational monitoring and control beyond deployment. The targeted correction is “Use the operate activity to maintain the live product and service under agreed operating conditions”.

D:

The proposed action focuses on a control governed by: Obtaining a component and implementing the complete solution are related but distinct activities. In this question the binding condition is: Sustained live performance depends on operational monitoring and control beyond deployment. Applying “Use the operate activity to maintain the live product and service under agreed operating conditions” addresses that specific cause instead.

Question 87

A company has a functional product but subscription entitlements and consumer access are not fulfilled correctly. Which approach most directly addresses the issue?

  1. Coordinate discover, design and acquire around required outcomes before implementation.
  2. Return to discover and design and then build and transition the improvement iteratively.
  3. Use the deliver activity to make the agreed product/service available to the consumer.
  4. Plan operational adoption, service readiness and safe rollout as transition outcomes.

Explanation

Correct Answer

C:

This intervention is directed at the cause: the capability exists, but consumers have not received the agreed service access or fulfilment. Confirm its value by checking that eligible customers receive the correct service entitlements.

Incorrect Answers

A:

This option would change the part of the system described by: Buying or building should follow a coherent understanding of needs and feasibility. The reported behavior instead arises because the capability exists, but consumers have not received the agreed service access or fulfilment. The direct remediation is “Use the deliver activity to make the agreed product/service available to the consumer”.

B:

Lifecycle activities can repeat in response to real user needs. That explains why “Return to discover and design and then build and transition the improvement iteratively” is useful for its own dependency, but the present failure follows a different constraint: The capability exists, but consumers have not received the agreed service access or fulfilment. The targeted correction is “Use the deliver activity to make the agreed product/service available to the consumer”.

D:

“Plan operational adoption, service readiness and safe rollout as transition outcomes” acts on a neighboring technical dependency: Code storage is part of implementation work but not full service introduction. It does not resolve the stated condition, whose causal mechanism is: The capability exists, but consumers have not received the agreed service access or fulfilment. The required action is “Use the deliver activity to make the agreed product/service available to the consumer”.

Question 88

A remote-working service is available but employees cannot get help after a password-reset failure. Which step best supports the intended result?

  1. Coordinate build and transition with adoption, training and cutover preparations.
  2. Use the support activity to help users and restore effective service consumption.
  3. Coordinate discover, design and acquire around required outcomes before implementation.
  4. Link build verification with deliver fulfilment and consumer access testing.

Explanation

Correct Answer

B:

This approach addresses the underlying concern: ongoing assistance and issue resolution are needed after delivery. A successful result would be that users obtain timely resolution and resume their work.

Incorrect Answers

A:

This approach addresses the underlying concern: a working implementation is not equivalent to successful entry into service. That explains why “Coordinate build and transition with adoption, training and cutover preparations” is useful for its own dependency, but the present failure follows a different constraint: This approach addresses the underlying concern: ongoing assistance and issue resolution are needed after delivery. The targeted correction is “Use the support activity to help users and restore effective service consumption”.

C:

“Coordinate discover, design and acquire around required outcomes before implementation” acts on a neighboring technical dependency: Buying or building should follow a coherent understanding of needs and feasibility. It does not resolve the stated condition, whose causal mechanism is: This approach addresses the underlying concern: ongoing assistance and issue resolution are needed after delivery. The required action is “Use the support activity to help users and restore effective service consumption”.

D:

This option would change the part of the system described by: Technical readiness and entitlement delivery are separate success requirements. The reported behavior instead arises because this approach addresses the underlying concern: ongoing assistance and issue resolution are needed after delivery. The direct remediation is “Use the support activity to help users and restore effective service consumption”.

Question 89

A healthcare platform revisits its feature design after deployment reveals accessibility problems. Which approach most directly addresses the issue?

  1. Connect support findings to discover, design and build priorities.
  2. Iterate between operate, discover and design as new evidence emerges.
  3. Separate deliver from operate and strengthen operating controls.
  4. Link build verification with deliver fulfilment and consumer access testing.

Explanation

Correct Answer

B:

The problem arises because the lifecycle is not a one-way sequence with discovery permanently finished after launch. The proposed change targets that cause; verify that the revised design improves accessibility in the live product.

Incorrect Answers

A:

The proposed action focuses on a control governed by: This approach addresses the underlying concern: issues uncovered during support should influence improvements rather than ending at ticket closure. In this question the binding condition is: The lifecycle is not a one-way sequence with discovery permanently finished after launch. Applying “Iterate between operate, discover and design as new evidence emerges” addresses that specific cause instead.

C:

This option would change the part of the system described by: Making a service available does not guarantee performance throughout use. The reported behavior instead arises because the lifecycle is not a one-way sequence with discovery permanently finished after launch. The direct remediation is “Iterate between operate, discover and design as new evidence emerges”.

D:

Technical readiness and entitlement delivery are separate success requirements. That explains why “Link build verification with deliver fulfilment and consumer access testing” is useful for its own dependency, but the present failure follows a different constraint: The lifecycle is not a one-way sequence with discovery permanently finished after launch. The targeted correction is “Iterate between operate, discover and design as new evidence emerges”.

Question 90

A travel agency assumes every acquisition decision must occur before any design work can begin. Which step best supports the intended result?

  1. Allow design and acquisition to inform each other iteratively as supplier capability is learned.
  2. Use the operate activity to maintain the live product and service under agreed operating conditions.
  3. Return to discover and design and then build and transition the improvement iteratively.
  4. Use acquire for the partner capability and build for integration into the firm's service.

Explanation

Correct Answer

A:

The response is relevant because lifecycle activities are interconnected and not strictly linear stages. It should produce a result in which supplier constraints are reflected in an acceptable final design.

Incorrect Answers

B:

This option would change the part of the system described by: Sustained live performance depends on operational monitoring and control beyond deployment. The reported behavior instead arises because lifecycle activities are interconnected and not strictly linear stages. The direct remediation is “Allow design and acquisition to inform each other iteratively as supplier capability is learned”.

C:

Lifecycle activities can repeat in response to real user needs. That explains why “Return to discover and design and then build and transition the improvement iteratively” is useful for its own dependency, but the present failure follows a different constraint: Lifecycle activities are interconnected and not strictly linear stages. The targeted correction is “Allow design and acquisition to inform each other iteratively as supplier capability is learned”.

D:

The proposed action focuses on a control governed by: Obtaining a component and implementing the complete solution are related but distinct activities. In this question the binding condition is: Lifecycle activities are interconnected and not strictly linear stages. Applying “Allow design and acquisition to inform each other iteratively as supplier capability is learned” addresses that specific cause instead.