Question 100
At the Cedar manufacturing group during a controlled pilot, a managed solution works in development but still calls the development endpoint after import into production. The project team must verify a scoped fix before rollout. Which ongoing engineering control would most directly reduce recurrence?
Explanation
Correct Answer
This routine prevents recurrence: require deployment-time validation of each environment variable. It targets the recurring risk created because hard-coded development URLs survive environment promotion. In the Cedar manufacturing group, assess this against the documented environment-specific endpoints scenario.
Incorrect Answers
That safeguard is appropriate for maintaining managed solution layering. It would not primarily prevent the reported failure, for which the relevant control is to require deployment-time validation of each environment variable. For case R082-PL400-CASE-0025, the decisive context is the 1 deployment setting at the Cedar manufacturing group.
This monitoring or review practice targets dependency-aware packaging; the better ongoing protection for this case is to require deployment-time validation of each environment variable. For case R082-PL400-CASE-0025, the decisive context is the 1 deployment setting at the Cedar manufacturing group.
“Track virtual-table provider capabilities and unsupported operations before enhancements” checks a different ongoing risk rather than the reported failure: at the Cedar manufacturing group during a controlled pilot, a managed solution works in development but still calls the development endpoint after import into production. The project team must verify a scoped fix before rollout. The relevant mechanism is hard-coded development URLs survive environment promotion. The directly matched preventive control is “Require deployment-time validation of each environment variable”.