Question 100
In a fictional CAPM project situation, a product owner orders detailed task assignments for a sprint rather than agreeing on desired outcomes. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: Scrum separates product ordering from developer planning autonomy. Consequently, the targeted action is: Have developers plan how to deliver selected work while the product owner clarifies value. This reasoning can be checked against: The sprint plan contains a shared goal and developer-owned delivery approach.
Incorrect Answers
“Scrum Master accountability is team effectiveness, not ownership of product value order” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum Master personally accepts or rejects all product scope requests before the product owner sees them. There the technical reason is: Scrum Master accountability is team effectiveness, not ownership of product value order. In this question, the reported issue is: In a fictional CAPM project situation, a product owner orders detailed task assignments for a sprint rather than agreeing on desired outcomes. The controlling principle is instead: Scrum separates product ordering from developer planning autonomy.
“The Sprint Review is a working session to inspect outcomes and adapt plans” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum team turns the Sprint Review into a manager's status presentation without product feedback. There the technical reason is: The Sprint Review is a working session to inspect outcomes and adapt plans. In this question, the reported issue is: In a fictional CAPM project situation, a product owner orders detailed task assignments for a sprint rather than agreeing on desired outcomes. The controlling principle is instead: Scrum separates product ordering from developer planning autonomy.
“The retrospective examines team effectiveness rather than proving product acceptance” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum team meets at sprint end only to assign blame for defects. There the technical reason is: The retrospective examines team effectiveness rather than proving product acceptance. In this question, the reported issue is: In a fictional CAPM project situation, a product owner orders detailed task assignments for a sprint rather than agreeing on desired outcomes. The controlling principle is instead: Scrum separates product ordering from developer planning autonomy.