McAfee Secure

PMI CAPM Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Training Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Training Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 13

Question 120

In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Refresh stakeholder mapping whenever scope or external conditions change.
  2. Validate milestones against upstream work and acceptance evidence.
  3. Periodically level resource demand and confirm specialists before commitment.
  4. Review critical supplier risks during milestones and update contingencies.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies. It follows the targeted action (register the vendor dependency with impact, response owner, and contingency action.) and provides a way to catch recurrence. The underlying principle is: Planning for uncertainty is more effective before the vendor fails.

Incorrect Answers

A:

“Refresh stakeholder mapping whenever scope or external conditions change” addresses recurrence of another problem: In a fictional CAPM project situation, a regional policy project has many regulators, but the team records only the funding sponsor as stakeholder. That problem depends on: This ongoing practice maintains the improvement: Refresh stakeholder mapping whenever scope or external conditions change. The recurring risk here is: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. The more targeted safeguard is “Review critical supplier risks during milestones and update contingencies” because this ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies.

B:

“Validate milestones against upstream work and acceptance evidence” addresses recurrence of another problem: In a fictional CAPM project situation, a mobile app launch plan shows a zero-day security signoff as if it were a two-week development task. That problem depends on: This ongoing practice maintains the improvement: Validate milestones against upstream work and acceptance evidence. The recurring risk here is: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. The more targeted safeguard is “Review critical supplier risks during milestones and update contingencies” because this ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies.

C:

“Periodically level resource demand and confirm specialists before commitment” addresses recurrence of another problem: In a fictional CAPM project situation, a manufacturing refit schedules three technicians for eight simultaneous specialized calibrations. That problem depends on: This ongoing practice maintains the improvement: Periodically level resource demand and confirm specialists before commitment. The recurring risk here is: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. The more targeted safeguard is “Review critical supplier risks during milestones and update contingencies” because this ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies.

Question 121

In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Maintain an approval matrix and escalation thresholds.
  2. Use transparent risk-adjusted forecasts and change thresholds.
  3. Use clear decision rights for technical and business choices.
  4. Use regular team check-ins and psychologically safe escalation.

Explanation

Correct Answer

B:

This ongoing practice maintains the improvement: Use transparent risk-adjusted forecasts and change thresholds. It follows the targeted action (explain the evidence-based forecast, options, and decisions requiring sponsor support.) and provides a way to catch recurrence. The underlying principle is: Sponsors make major business trade-offs; project managers provide reliable delivery information.

Incorrect Answers

A:

“Maintain an approval matrix and escalation thresholds” addresses recurrence of another problem: In a fictional CAPM project situation, a sponsor asks a project coordinator to authorize funding outside an agreed approval threshold. That problem depends on: This ongoing practice maintains the improvement: Maintain an approval matrix and escalation thresholds. The recurring risk here is: In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. The more targeted safeguard is “Use transparent risk-adjusted forecasts and change thresholds” because this ongoing practice maintains the improvement: Use transparent risk-adjusted forecasts and change thresholds.

C:

“Use clear decision rights for technical and business choices” addresses recurrence of another problem: In a fictional CAPM project situation, a team cannot resolve a technical design trade-off, and its sponsor wants to select the implementation detail personally. That problem depends on: This ongoing practice maintains the improvement: Use clear decision rights for technical and business choices. The recurring risk here is: In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. The more targeted safeguard is “Use transparent risk-adjusted forecasts and change thresholds” because this ongoing practice maintains the improvement: Use transparent risk-adjusted forecasts and change thresholds.

D:

“Use regular team check-ins and psychologically safe escalation” addresses recurrence of another problem: In a fictional CAPM project situation, a municipal project team blames an absent analyst for late requirements and avoids discussing blockers. That problem depends on: This ongoing practice maintains the improvement: Use regular team check-ins and psychologically safe escalation. The recurring risk here is: In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. The more targeted safeguard is “Use transparent risk-adjusted forecasts and change thresholds” because this ongoing practice maintains the improvement: Use transparent risk-adjusted forecasts and change thresholds.

Question 122

In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. What evidence would most directly demonstrate that the appropriate response was effective?

  1. A dated notification receipt and incident record demonstrate timely compliance.
  2. Defect metrics meet the trigger and approved response actions are recorded.
  3. The dashboard agrees with underlying schedule, cost, and risk evidence.
  4. An approved plan defines baseline consumption, target, and measurement period.

Explanation

Correct Answer

B:

The specified evidence tests the exact improvement at issue: Defect metrics meet the trigger and approved response actions are recorded. It supports the chosen response (execute the documented contingent supplier response and inform the risk owner.) rather than merely recording activity. The principle is: A predefined response should be activated when its monitored trigger occurs.

Incorrect Answers

A:

“A dated notification receipt and incident record demonstrate timely compliance” is evidence for a different source case: In a fictional CAPM project situation, a regulator must be informed within two working days of a material incident under the communication plan. Its related mechanism is: A communications strategy defines required audiences, timing, and media. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. The source-keyed acceptance evidence is “Defect metrics meet the trigger and approved response actions are recorded”.

C:

“The dashboard agrees with underlying schedule, cost, and risk evidence” is evidence for a different source case: In a fictional CAPM project situation, a project has a weekly executive dashboard but changes the status color to green to avoid concern. Its related mechanism is: Communication plans do not justify distorting performance information. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. The source-keyed acceptance evidence is “Defect metrics meet the trigger and approved response actions are recorded”.

D:

“An approved plan defines baseline consumption, target, and measurement period” is evidence for a different source case: In a fictional CAPM project situation, a campus building project has promised energy savings, but baseline utility consumption was never captured. Its related mechanism is: Benefits realization requires comparing observed outcomes with a valid baseline. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. The source-keyed acceptance evidence is “Defect metrics meet the trigger and approved response actions are recorded”.

Question 123

In a fictional CAPM project situation, a coordinator uses performance reports to pressure a burned-out team rather than removing obstacles. Which underlying project-management principle best explains the appropriate response?

  1. Without defined decision rights, approval work falls between participants.
  2. Leadership develops capability and trust; metrics alone do not motivate teams.
  3. Escalation should follow materiality and decision rights, not bypass delegation.
  4. Listening and empathy expose valid concerns that defensiveness can hide.

Explanation

Correct Answer

B:

The case turns on this distinction: Leadership develops capability and trust; metrics alone do not motivate teams. Consequently, the targeted action is: Coach the team, address impediments, and rebalance commitments with transparency. This reasoning can be checked against: Workload trends and team feedback show a manageable sustainable pace.

Incorrect Answers

A:

“Without defined decision rights, approval work falls between participants” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a distributed project reports tasks complete, but nobody owns the final regulatory signoff. There the technical reason is: Without defined decision rights, approval work falls between participants. In this question, the reported issue is: In a fictional CAPM project situation, a coordinator uses performance reports to pressure a burned-out team rather than removing obstacles. The controlling principle is instead: Leadership develops capability and trust; metrics alone do not motivate teams.

C:

“Escalation should follow materiality and decision rights, not bypass delegation” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a construction architect asks the sponsor to approve routine drawing corrections already delegated to the lead engineer. There the technical reason is: Escalation should follow materiality and decision rights, not bypass delegation. In this question, the reported issue is: In a fictional CAPM project situation, a coordinator uses performance reports to pressure a burned-out team rather than removing obstacles. The controlling principle is instead: Leadership develops capability and trust; metrics alone do not motivate teams.

D:

“Listening and empathy expose valid concerns that defensiveness can hide” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, an operations representative raises a serious usability concern and the project manager dismisses it as resistance. There the technical reason is: Listening and empathy expose valid concerns that defensiveness can hide. In this question, the reported issue is: In a fictional CAPM project situation, a coordinator uses performance reports to pressure a burned-out team rather than removing obstacles. The controlling principle is instead: Leadership develops capability and trust; metrics alone do not motivate teams.

Question 124

In a fictional CAPM project situation, a bridge team knows seasonal flooding might delay concrete deliveries, but no flooding has occurred. Which underlying project-management principle best explains the appropriate response?

  1. An event that has occurred is an issue, not merely a future risk.
  2. A risk is uncertain; an issue is an event already affecting the work.
  3. An assumption is treated as true for planning but may be unverified.
  4. A constraint limits permissible project choices; it is not an uncertain event.

Explanation

Correct Answer

B:

The case turns on this distinction: A risk is uncertain; an issue is an event already affecting the work. Consequently, the targeted action is: Record the possible flood as a risk with probability, impact, owner, and response trigger. This reasoning can be checked against: The risk register contains a future uncertainty and a monitored trigger rather than an incident ticket.

Incorrect Answers

A:

“An event that has occurred is an issue, not merely a future risk” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a supplier has already missed a required cybersecurity inspection, stopping acceptance today. There the technical reason is: An event that has occurred is an issue, not merely a future risk. In this question, the reported issue is: In a fictional CAPM project situation, a bridge team knows seasonal flooding might delay concrete deliveries, but no flooding has occurred. The controlling principle is instead: A risk is uncertain; an issue is an event already affecting the work.

C:

“An assumption is treated as true for planning but may be unverified” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a clinic plans to use a free meeting room based only on an unconfirmed facilities promise. There the technical reason is: An assumption is treated as true for planning but may be unverified. In this question, the reported issue is: In a fictional CAPM project situation, a bridge team knows seasonal flooding might delay concrete deliveries, but no flooding has occurred. The controlling principle is instead: A risk is uncertain; an issue is an event already affecting the work.

D:

“A constraint limits permissible project choices; it is not an uncertain event” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a museum must open its exhibit before a legislated anniversary, and the date cannot move. There the technical reason is: A constraint limits permissible project choices; it is not an uncertain event. In this question, the reported issue is: In a fictional CAPM project situation, a bridge team knows seasonal flooding might delay concrete deliveries, but no flooding has occurred. The controlling principle is instead: A risk is uncertain; an issue is an event already affecting the work.

Question 125

In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The traceable communication record shows each impacted group acknowledged the requirement.
  2. Customer testers acknowledge the current version and updated acceptance scenarios.
  3. Participants can access current status and spend meeting time on unresolved issues.
  4. Regional representatives confirm comprehension and consistent policy interpretation.

Explanation

Correct Answer

A:

The specified evidence tests the exact improvement at issue: The traceable communication record shows each impacted group acknowledged the requirement. It supports the chosen response (notify product, operations, compliance, and delivery stakeholders using agreed channels.) rather than merely recording activity. The principle is: Requirements information must reach every role whose work or decision it changes.

Incorrect Answers

B:

“Customer testers acknowledge the current version and updated acceptance scenarios” is evidence for a different source case: In a fictional CAPM project situation, a team announces changed acceptance criteria during a release call without telling customer testers in advance. Its related mechanism is: Uncontrolled communication creates inconsistent acceptance expectations. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. The source-keyed acceptance evidence is “The traceable communication record shows each impacted group acknowledged the requirement”.

C:

“Participants can access current status and spend meeting time on unresolved issues” is evidence for a different source case: In a fictional CAPM project situation, a remote engineering team uses lengthy meetings to resolve simple status questions across time zones. Its related mechanism is: Communication media should be proportionate to complexity and urgency. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. The source-keyed acceptance evidence is “The traceable communication record shows each impacted group acknowledged the requirement”.

D:

“Regional representatives confirm comprehension and consistent policy interpretation” is evidence for a different source case: In a fictional CAPM project situation, a multinational employee system announces policy changes through one-language email despite local users with different needs. Its related mechanism is: A sent message is ineffective if recipients cannot act on it accurately. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. The source-keyed acceptance evidence is “The traceable communication record shows each impacted group acknowledged the requirement”.

Question 126

In a fictional CAPM project situation, a team calls every five-minute daily sync a Sprint Planning meeting. Which underlying project-management principle best explains the appropriate response?

  1. Scrum separates product ordering from developer planning autonomy.
  2. Scrum Master accountability is team effectiveness, not ownership of product value order.
  3. Scrum events have distinct purposes and should not be conflated.
  4. The Sprint Review is a working session to inspect outcomes and adapt plans.

Explanation

Correct Answer

C:

The case turns on this distinction: Scrum events have distinct purposes and should not be conflated. Consequently, the targeted action is: Use Sprint Planning for defining the Sprint Goal and selecting work; use Daily Scrum for progress toward that goal. This reasoning can be checked against: Planning produces a Sprint Goal and sprint backlog, while daily coordination adapts the plan.

Incorrect Answers

A:

“Scrum separates product ordering from developer planning autonomy” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a product owner orders detailed task assignments for a sprint rather than agreeing on desired outcomes. There the technical reason is: Scrum separates product ordering from developer planning autonomy. In this question, the reported issue is: In a fictional CAPM project situation, a team calls every five-minute daily sync a Sprint Planning meeting. The controlling principle is instead: Scrum events have distinct purposes and should not be conflated.

B:

“Scrum Master accountability is team effectiveness, not ownership of product value order” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum Master personally accepts or rejects all product scope requests before the product owner sees them. There the technical reason is: Scrum Master accountability is team effectiveness, not ownership of product value order. In this question, the reported issue is: In a fictional CAPM project situation, a team calls every five-minute daily sync a Sprint Planning meeting. The controlling principle is instead: Scrum events have distinct purposes and should not be conflated.

D:

“The Sprint Review is a working session to inspect outcomes and adapt plans” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a Scrum team turns the Sprint Review into a manager's status presentation without product feedback. There the technical reason is: The Sprint Review is a working session to inspect outcomes and adapt plans. In this question, the reported issue is: In a fictional CAPM project situation, a team calls every five-minute daily sync a Sprint Planning meeting. The controlling principle is instead: Scrum events have distinct purposes and should not be conflated.

Question 127

In a fictional CAPM project situation, a research team has safe deployment automation but waits six months to show working software. Which underlying project-management principle best explains the appropriate response?

  1. Uncertain requirements fit shorter feedback cycles when governance allows them.
  2. Automation and engaged stakeholders are assets that support adaptive flow.
  3. Interrupt-driven work may be managed better through flow than fixed batches.
  4. Exploratory product uncertainty favors iterative learning over rigid full-detail plans.

Explanation

Correct Answer

B:

The case turns on this distinction: Automation and engaged stakeholders are assets that support adaptive flow. Consequently, the targeted action is: Use the existing automated deployment capability to deliver smaller validated increments. This reasoning can be checked against: Deployment records and stakeholder demos show frequent usable results.

Incorrect Answers

A:

“Uncertain requirements fit shorter feedback cycles when governance allows them” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a government service product has unstable user needs but its contract fixes every feature detail upfront. There the technical reason is: Uncertain requirements fit shorter feedback cycles when governance allows them. In this question, the reported issue is: In a fictional CAPM project situation, a research team has safe deployment automation but waits six months to show working software. The controlling principle is instead: Automation and engaged stakeholders are assets that support adaptive flow.

C:

“Interrupt-driven work may be managed better through flow than fixed batches” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a mature maintenance team has repetitive urgent tickets arriving continuously, and sprint commitment frequently collapses. There the technical reason is: Interrupt-driven work may be managed better through flow than fixed batches. In this question, the reported issue is: In a fictional CAPM project situation, a research team has safe deployment automation but waits six months to show working software. The controlling principle is instead: Automation and engaged stakeholders are assets that support adaptive flow.

D:

“Exploratory product uncertainty favors iterative learning over rigid full-detail plans” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. There the technical reason is: Exploratory product uncertainty favors iterative learning over rigid full-detail plans. In this question, the reported issue is: In a fictional CAPM project situation, a research team has safe deployment automation but waits six months to show working software. The controlling principle is instead: Automation and engaged stakeholders are assets that support adaptive flow.

Question 128

In a fictional CAPM project situation, a municipal bridge program treats delivery of approved drawings as equivalent to completed construction. Which underlying project-management principle best explains the appropriate response?

  1. High retooling cost favors early requirements confirmation and formal change control.
  2. Project components represent different outcomes and must not be conflated.
  3. Irreversible hardware interfaces require deliberate baseline control.
  4. Stable external specifications and expensive changes make predictive planning suitable.

Explanation

Correct Answer

B:

The case turns on this distinction: Project components represent different outcomes and must not be conflated. Consequently, the targeted action is: Distinguish design deliverables, construction work packages, and final accepted assets. This reasoning can be checked against: The work breakdown and acceptance register separately track drawing and built-work completion.

Incorrect Answers

A:

“High retooling cost favors early requirements confirmation and formal change control” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. There the technical reason is: High retooling cost favors early requirements confirmation and formal change control. In this question, the reported issue is: In a fictional CAPM project situation, a municipal bridge program treats delivery of approved drawings as equivalent to completed construction. The controlling principle is instead: Project components represent different outcomes and must not be conflated.

C:

“Irreversible hardware interfaces require deliberate baseline control” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. There the technical reason is: Irreversible hardware interfaces require deliberate baseline control. In this question, the reported issue is: In a fictional CAPM project situation, a municipal bridge program treats delivery of approved drawings as equivalent to completed construction. The controlling principle is instead: Project components represent different outcomes and must not be conflated.

D:

“Stable external specifications and expensive changes make predictive planning suitable” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a regulated laboratory must build equipment to a frozen specification with physical validation gates and costly rework. There the technical reason is: Stable external specifications and expensive changes make predictive planning suitable. In this question, the reported issue is: In a fictional CAPM project situation, a municipal bridge program treats delivery of approved drawings as equivalent to completed construction. The controlling principle is instead: Project components represent different outcomes and must not be conflated.

Question 129

In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Perform engineering integration reviews before configuration changes.
  2. Control baseline amendments through integrated approval and validation.
  3. Enforce entry and exit criteria for each planned phase.
  4. Review capacity conflicts with functional managers before baselines change.

Explanation

Correct Answer

A:

This ongoing practice maintains the improvement: Perform engineering integration reviews before configuration changes. It follows the targeted action (set a predictive integration plan and approved configuration baseline.) and provides a way to catch recurrence. The underlying principle is: Irreversible hardware interfaces require deliberate baseline control.

Incorrect Answers

B:

“Control baseline amendments through integrated approval and validation” addresses recurrence of another problem: In a fictional CAPM project situation, a regulated laboratory must build equipment to a frozen specification with physical validation gates and costly rework. That problem depends on: This ongoing practice maintains the improvement: Control baseline amendments through integrated approval and validation. The recurring risk here is: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. The more targeted safeguard is “Perform engineering integration reviews before configuration changes” because this ongoing practice maintains the improvement: Perform engineering integration reviews before configuration changes.

C:

“Enforce entry and exit criteria for each planned phase” addresses recurrence of another problem: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. That problem depends on: This ongoing practice maintains the improvement: Enforce entry and exit criteria for each planned phase. The recurring risk here is: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. The more targeted safeguard is “Perform engineering integration reviews before configuration changes” because this ongoing practice maintains the improvement: Perform engineering integration reviews before configuration changes.

D:

“Review capacity conflicts with functional managers before baselines change” addresses recurrence of another problem: In a fictional CAPM project situation, a matrix organization lends mechanical engineers to two simultaneous capital projects without resource commitments. That problem depends on: This ongoing practice maintains the improvement: Review capacity conflicts with functional managers before baselines change. The recurring risk here is: In a fictional CAPM project situation, a satellite hardware project has fixed launch integration dates but reorders design decisions daily without change records. The more targeted safeguard is “Perform engineering integration reviews before configuration changes” because this ongoing practice maintains the improvement: Perform engineering integration reviews before configuration changes.

Question 130

In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Add documentation dependencies to schedule reviews.
  2. Define service readiness criteria before launch approval.
  3. Track contingency use and periodically reassess probability.
  4. Monitor shared specialist calendars in rolling-wave planning.

Explanation

Correct Answer

A:

This ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews. It follows the targeted action (update the dependency network to include mandatory calibration evidence before acceptance.) and provides a way to catch recurrence. The underlying principle is: Acceptance cannot occur before its required supporting evidence is ready.

Incorrect Answers

B:

“Define service readiness criteria before launch approval” addresses recurrence of another problem: In a fictional CAPM project situation, a new customer service center's opening plan includes equipment deliveries but excludes employee training readiness. That problem depends on: This ongoing practice maintains the improvement: Define service readiness criteria before launch approval. The recurring risk here is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The more targeted safeguard is “Add documentation dependencies to schedule reviews” because this ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews.

C:

“Track contingency use and periodically reassess probability” addresses recurrence of another problem: In a fictional CAPM project situation, a school software project lists a possible translation delay but never budgets response time for it. That problem depends on: This ongoing practice maintains the improvement: Track contingency use and periodically reassess probability. The recurring risk here is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The more targeted safeguard is “Add documentation dependencies to schedule reviews” because this ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews.

D:

“Monitor shared specialist calendars in rolling-wave planning” addresses recurrence of another problem: In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. That problem depends on: This ongoing practice maintains the improvement: Monitor shared specialist calendars in rolling-wave planning. The recurring risk here is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The more targeted safeguard is “Add documentation dependencies to schedule reviews” because this ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews.