Question 120
In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. Which continuing control would most directly reduce the chance of this problem recurring?
Explanation
Correct Answer
This ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies. It follows the targeted action (register the vendor dependency with impact, response owner, and contingency action.) and provides a way to catch recurrence. The underlying principle is: Planning for uncertainty is more effective before the vendor fails.
Incorrect Answers
“Refresh stakeholder mapping whenever scope or external conditions change” addresses recurrence of another problem: In a fictional CAPM project situation, a regional policy project has many regulators, but the team records only the funding sponsor as stakeholder. That problem depends on: This ongoing practice maintains the improvement: Refresh stakeholder mapping whenever scope or external conditions change. The recurring risk here is: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. The more targeted safeguard is “Review critical supplier risks during milestones and update contingencies” because this ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies.
“Validate milestones against upstream work and acceptance evidence” addresses recurrence of another problem: In a fictional CAPM project situation, a mobile app launch plan shows a zero-day security signoff as if it were a two-week development task. That problem depends on: This ongoing practice maintains the improvement: Validate milestones against upstream work and acceptance evidence. The recurring risk here is: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. The more targeted safeguard is “Review critical supplier risks during milestones and update contingencies” because this ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies.
“Periodically level resource demand and confirm specialists before commitment” addresses recurrence of another problem: In a fictional CAPM project situation, a manufacturing refit schedules three technicians for eight simultaneous specialized calibrations. That problem depends on: This ongoing practice maintains the improvement: Periodically level resource demand and confirm specialists before commitment. The recurring risk here is: In a fictional CAPM project situation, a data-center migration identifies a single power vendor whose outage could delay the move. The more targeted safeguard is “Review critical supplier risks during milestones and update contingencies” because this ongoing practice maintains the improvement: Review critical supplier risks during milestones and update contingencies.