Question 130
In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. Which continuing control would most directly reduce the chance of this problem recurring?
Explanation
Correct Answer
This ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews. It follows the targeted action (update the dependency network to include mandatory calibration evidence before acceptance.) and provides a way to catch recurrence. The underlying principle is: Acceptance cannot occur before its required supporting evidence is ready.
Incorrect Answers
“Define service readiness criteria before launch approval” addresses recurrence of another problem: In a fictional CAPM project situation, a new customer service center's opening plan includes equipment deliveries but excludes employee training readiness. That problem depends on: This ongoing practice maintains the improvement: Define service readiness criteria before launch approval. The recurring risk here is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The more targeted safeguard is “Add documentation dependencies to schedule reviews” because this ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews.
“Track contingency use and periodically reassess probability” addresses recurrence of another problem: In a fictional CAPM project situation, a school software project lists a possible translation delay but never budgets response time for it. That problem depends on: This ongoing practice maintains the improvement: Track contingency use and periodically reassess probability. The recurring risk here is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The more targeted safeguard is “Add documentation dependencies to schedule reviews” because this ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews.
“Monitor shared specialist calendars in rolling-wave planning” addresses recurrence of another problem: In a fictional CAPM project situation, a campus renovation has several overlapping electrical inspections and no identified inspector availability. That problem depends on: This ongoing practice maintains the improvement: Monitor shared specialist calendars in rolling-wave planning. The recurring risk here is: In a fictional CAPM project situation, a laboratory project schedules acceptance before calibration certificates from the supplier will be available. The more targeted safeguard is “Add documentation dependencies to schedule reviews” because this ongoing practice maintains the improvement: Add documentation dependencies to schedule reviews.