Question 240
In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. Which action most directly addresses the problem while respecting the relevant roles and constraints?
Explanation
Correct Answer
This directly addresses the case's governing problem: Plan an independent vertical slice or address the dependency before committing the blocked feature. The key reason is that undisclosed dependencies undermine a credible iteration plan. A suitable completion check is: Dependency records and sprint forecast show achievable ready work.
Incorrect Answers
“Slice the deliverable into independently demonstrable user outcomes with acceptance criteria” responds to another technical or business failure: In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. That source case depends on: Adaptive planning emphasizes small, coherent increments of user value. The present issue is: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The more direct action is “Plan an independent vertical slice or address the dependency before committing the blocked feature” because undisclosed dependencies undermine a credible iteration plan.
“Track completed usable increments, flow, and value evidence alongside forecasts” responds to another technical or business failure: In a fictional CAPM project situation, a team uses the percentage of a fixed annual scope completed as the only indicator of adaptive progress. That source case depends on: Adaptive progress is better evidenced through usable value than unvalidated activity percentages. The present issue is: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The more direct action is “Plan an independent vertical slice or address the dependency before committing the blocked feature” because undisclosed dependencies undermine a credible iteration plan.
“Negotiate scope with the developers while safeguarding a coherent Sprint Goal” responds to another technical or business failure: In a fictional CAPM project situation, a product owner announces a new urgent feature mid-sprint and demands that the Sprint Goal stay unchanged without discussion. That source case depends on: Sprint scope can be clarified and renegotiated while the Sprint Goal provides focus. The present issue is: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The more direct action is “Plan an independent vertical slice or address the dependency before committing the blocked feature” because undisclosed dependencies undermine a credible iteration plan.