Question 260
In a fictional CAPM project situation, a clinic schedules go-live despite an unresolved high-severity medication data mapping defect. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: Defect and test records show the criterion is met before approval. It supports the chosen response (hold or escalate the release decision against the defined safety acceptance threshold.) rather than merely recording activity. The principle is: High-risk unaccepted defects invalidate readiness even if most features are complete.
Incorrect Answers
“Signed user acceptance results cover guardian permissions and enrollment tasks” is evidence for a different source case: In a fictional CAPM project situation, a school enrollment system is tested only with administrator accounts; guardian workflows are unverified. Its related mechanism is: A requirement is not verified by testing a different actor's workflow. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a clinic schedules go-live despite an unresolved high-severity medication data mapping defect. The source-keyed acceptance evidence is “Defect and test records show the criterion is met before approval”.
“Tests prove expected end date, charges, confirmation, and edge cases” is evidence for a different source case: In a fictional CAPM project situation, a subscription product releases a cancellation feature whose acceptance criteria merely state 'works correctly'. Its related mechanism is: Unmeasurable criteria make acceptance subjective and hard to defend. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a clinic schedules go-live despite an unresolved high-severity medication data mapping defect. The source-keyed acceptance evidence is “Defect and test records show the criterion is met before approval”.
“Load-test reports show response time under the agreed demand profile” is evidence for a different source case: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. Its related mechanism is: Functional completion cannot replace nonfunctional acceptance evidence. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a clinic schedules go-live despite an unresolved high-severity medication data mapping defect. The source-keyed acceptance evidence is “Defect and test records show the criterion is met before approval”.