Question 270
In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: Sponsors make major business trade-offs; project managers provide reliable delivery information. Consequently, the targeted action is: Explain the evidence-based forecast, options, and decisions requiring sponsor support. This reasoning can be checked against: A signed steering decision records forecast assumptions and trade-offs.
Incorrect Answers
“Project managers coordinate delivery; sponsors typically champion and authorize major resources” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a sponsor asks a project coordinator to authorize funding outside an agreed approval threshold. There the technical reason is: Project managers coordinate delivery; sponsors typically champion and authorize major resources. In this question, the reported issue is: In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. The controlling principle is instead: Sponsors make major business trade-offs; project managers provide reliable delivery information.
“Sponsors provide direction and resources, while project teams supply specialized delivery knowledge” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a team cannot resolve a technical design trade-off, and its sponsor wants to select the implementation detail personally. There the technical reason is: Sponsors provide direction and resources, while project teams supply specialized delivery knowledge. In this question, the reported issue is: In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. The controlling principle is instead: Sponsors make major business trade-offs; project managers provide reliable delivery information.
“Emotional intelligence supports listening and conflict resolution rather than blame” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a municipal project team blames an absent analyst for late requirements and avoids discussing blockers. There the technical reason is: Emotional intelligence supports listening and conflict resolution rather than blame. In this question, the reported issue is: In a fictional CAPM project situation, a sponsor challenges the project manager's forecast and expects a single optimistic date despite test failures. The controlling principle is instead: Sponsors make major business trade-offs; project managers provide reliable delivery information.