  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Training Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Training Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 29

Question 280

In a fictional CAPM project situation, a security team receives new data residency requirements after project authorization. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Test important contingency procedures and triggers in advance.
  2. Check communication effectiveness, not just message distribution.
  3. Continue outcome monitoring through the planned realization period.
  4. Monitor regulatory changes and perform periodic compliance reassessment.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Monitor regulatory changes and perform periodic compliance reassessment. It follows the targeted action (review compliance impact and update the initiation and delivery controls through governance.) and provides a way to catch recurrence. The underlying principle is: New external constraints can alter the project business case and obligations.

Incorrect Answers

A:

“Test important contingency procedures and triggers in advance” addresses recurrence of another problem: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. That problem depends on: This ongoing practice maintains the improvement: Test important contingency procedures and triggers in advance. The recurring risk here is: In a fictional CAPM project situation, a security team receives new data residency requirements after project authorization. The more targeted safeguard is “Monitor regulatory changes and perform periodic compliance reassessment” because this ongoing practice maintains the improvement: Monitor regulatory changes and perform periodic compliance reassessment.

B:

“Check communication effectiveness, not just message distribution” addresses recurrence of another problem: In a fictional CAPM project situation, a communications plan requires accessible summaries, yet a team shares only technical diagrams with community representatives. That problem depends on: This ongoing practice maintains the improvement: Check communication effectiveness, not just message distribution. The recurring risk here is: In a fictional CAPM project situation, a security team receives new data residency requirements after project authorization. The more targeted safeguard is “Monitor regulatory changes and perform periodic compliance reassessment” because this ongoing practice maintains the improvement: Monitor regulatory changes and perform periodic compliance reassessment.

C:

“Continue outcome monitoring through the planned realization period” addresses recurrence of another problem: In a fictional CAPM project situation, a sponsor expected reduced staff overtime after a new scheduling tool, but the benefit metric was never assigned. That problem depends on: This ongoing practice maintains the improvement: Continue outcome monitoring through the planned realization period. The recurring risk here is: In a fictional CAPM project situation, a security team receives new data residency requirements after project authorization. The more targeted safeguard is “Monitor regulatory changes and perform periodic compliance reassessment” because this ongoing practice maintains the improvement: Monitor regulatory changes and perform periodic compliance reassessment.

Question 281

In a fictional CAPM project situation, a Kanban repair team starts ten new tickets while older ones stay blocked. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Keep test coverage and build health visible to developers.
  2. Review integration dependencies and product-level priorities regularly.
  3. Keep each event timeboxed and evaluate whether it fulfills its purpose.
  4. Tune WIP limits using observed cycle time and capacity.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Tune WIP limits using observed cycle time and capacity. It follows the targeted action (apply explicit WIP limits and finish or unblock existing work before starting more.) and provides a way to catch recurrence. The underlying principle is: Excess WIP increases context switching and queues.

Incorrect Answers

A:

“Keep test coverage and build health visible to developers” addresses recurrence of another problem: In a fictional CAPM project situation, an XP-focused development team merges code without automated tests and finds regressions each week. That problem depends on: This ongoing practice maintains the improvement: Keep test coverage and build health visible to developers. The recurring risk here is: In a fictional CAPM project situation, a Kanban repair team starts ten new tickets while older ones stay blocked. The more targeted safeguard is “Tune WIP limits using observed cycle time and capacity” because this ongoing practice maintains the improvement: Tune WIP limits using observed cycle time and capacity.

B:

“Review integration dependencies and product-level priorities regularly” addresses recurrence of another problem: In a fictional CAPM project situation, two Scrum teams work on one product but maintain conflicting product goals and prioritization. That problem depends on: This ongoing practice maintains the improvement: Review integration dependencies and product-level priorities regularly. The recurring risk here is: In a fictional CAPM project situation, a Kanban repair team starts ten new tickets while older ones stay blocked. The more targeted safeguard is “Tune WIP limits using observed cycle time and capacity” because this ongoing practice maintains the improvement: Tune WIP limits using observed cycle time and capacity.

C:

“Keep each event timeboxed and evaluate whether it fulfills its purpose” addresses recurrence of another problem: In a fictional CAPM project situation, a team calls every five-minute daily sync a Sprint Planning meeting. That problem depends on: This ongoing practice maintains the improvement: Keep each event timeboxed and evaluate whether it fulfills its purpose. The recurring risk here is: In a fictional CAPM project situation, a Kanban repair team starts ten new tickets while older ones stay blocked. The more targeted safeguard is “Tune WIP limits using observed cycle time and capacity” because this ongoing practice maintains the improvement: Tune WIP limits using observed cycle time and capacity.

Question 282

In a fictional CAPM project situation, a manufacturing refit schedules three technicians for eight simultaneous specialized calibrations. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Use a closure checklist with a named operations owner.
  2. Make records retention and lessons capture mandatory closeout activities.
  3. Periodically level resource demand and confirm specialists before commitment.
  4. Reconcile plan components at change-control and phase-gate reviews.

Explanation

Correct Answer

C:

This ongoing practice maintains the improvement: Periodically level resource demand and confirm specialists before commitment. It follows the targeted action (reconcile resource skills and availability against the activity schedule.) and provides a way to catch recurrence. The underlying principle is: An activity plan is infeasible when required skills exceed available capacity.

Incorrect Answers

A:

“Use a closure checklist with a named operations owner” addresses recurrence of another problem: In a fictional CAPM project situation, a charity portal is being handed to support without runbooks or service-owner acceptance. That problem depends on: This ongoing practice maintains the improvement: Use a closure checklist with a named operations owner. The recurring risk here is: In a fictional CAPM project situation, a manufacturing refit schedules three technicians for eight simultaneous specialized calibrations. The more targeted safeguard is “Periodically level resource demand and confirm specialists before commitment” because this ongoing practice maintains the improvement: Periodically level resource demand and confirm specialists before commitment.

B:

“Make records retention and lessons capture mandatory closeout activities” addresses recurrence of another problem: In a fictional CAPM project situation, a marketing campaign closes by deleting its project workspace, losing lessons and procurement records. That problem depends on: This ongoing practice maintains the improvement: Make records retention and lessons capture mandatory closeout activities. The recurring risk here is: In a fictional CAPM project situation, a manufacturing refit schedules three technicians for eight simultaneous specialized calibrations. The more targeted safeguard is “Periodically level resource demand and confirm specialists before commitment” because this ongoing practice maintains the improvement: Periodically level resource demand and confirm specialists before commitment.

D:

“Reconcile plan components at change-control and phase-gate reviews” addresses recurrence of another problem: In a fictional CAPM project situation, a sensor-installation team plans only the product features and overlooks approvals, staffing, and risk response. That problem depends on: This ongoing practice maintains the improvement: Reconcile plan components at change-control and phase-gate reviews. The recurring risk here is: In a fictional CAPM project situation, a manufacturing refit schedules three technicians for eight simultaneous specialized calibrations. The more targeted safeguard is “Periodically level resource demand and confirm specialists before commitment” because this ongoing practice maintains the improvement: Periodically level resource demand and confirm specialists before commitment.

Question 283

In a fictional CAPM project situation, a team accepts vague stories as complete when only code is written, excluding documentation and testing. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Make guardrail requirements explicit in prioritization policy.
  2. Revisit priorities after new customer evidence arrives.
  3. Include acceptance examples during refinement and demonstrate them at review.
  4. Review Done criteria and keep story sizes small enough to finish.

Explanation

Correct Answer

D:

This ongoing practice maintains the improvement: Review Done criteria and keep story sizes small enough to finish. It follows the targeted action (apply the shared completion criteria before counting the user story delivered.) and provides a way to catch recurrence. The underlying principle is: Partial implementation does not meet the agreed quality bar.

Incorrect Answers

A:

“Make guardrail requirements explicit in prioritization policy” addresses recurrence of another problem: In a fictional CAPM project situation, a health-tech team defers critical data-protection work because its short-term story value score is lower than a new theme. That problem depends on: This ongoing practice maintains the improvement: Make guardrail requirements explicit in prioritization policy. The recurring risk here is: In a fictional CAPM project situation, a team accepts vague stories as complete when only code is written, excluding documentation and testing. The more targeted safeguard is “Review Done criteria and keep story sizes small enough to finish” because this ongoing practice maintains the improvement: Review Done criteria and keep story sizes small enough to finish.

B:

“Revisit priorities after new customer evidence arrives” addresses recurrence of another problem: In a fictional CAPM project situation, a backlog includes a feature with high customer impact and a cosmetic tweak; both are estimated equal effort. That problem depends on: This ongoing practice maintains the improvement: Revisit priorities after new customer evidence arrives. The recurring risk here is: In a fictional CAPM project situation, a team accepts vague stories as complete when only code is written, excluding documentation and testing. The more targeted safeguard is “Review Done criteria and keep story sizes small enough to finish” because this ongoing practice maintains the improvement: Review Done criteria and keep story sizes small enough to finish.

C:

“Include acceptance examples during refinement and demonstrate them at review” addresses recurrence of another problem: In a fictional CAPM project situation, an adaptive team releases a new booking feature but has no criteria to judge whether it works for users. That problem depends on: This ongoing practice maintains the improvement: Include acceptance examples during refinement and demonstrate them at review. The recurring risk here is: In a fictional CAPM project situation, a team accepts vague stories as complete when only code is written, excluding documentation and testing. The more targeted safeguard is “Review Done criteria and keep story sizes small enough to finish” because this ongoing practice maintains the improvement: Review Done criteria and keep story sizes small enough to finish.

Question 284

In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Require cross-functional impact checks for material design changes.
  2. Run schedule logic audits at each baseline review.
  3. Maintain traceability from deliverable scope to inspection evidence.
  4. Reassess critical-path dates when durations change.

Explanation

Correct Answer

A:

This ongoing practice maintains the improvement: Require cross-functional impact checks for material design changes. It follows the targeted action (evaluate the change across integrated plans before approval and implementation.) and provides a way to catch recurrence. The underlying principle is: Integration management keeps plan components internally consistent.

Incorrect Answers

B:

“Run schedule logic audits at each baseline review” addresses recurrence of another problem: In a fictional CAPM project situation, a rail signaling project has three activities dependent on a single final software test, but the test is absent from its network. That problem depends on: This ongoing practice maintains the improvement: Run schedule logic audits at each baseline review. The recurring risk here is: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. The more targeted safeguard is “Require cross-functional impact checks for material design changes” because this ongoing practice maintains the improvement: Require cross-functional impact checks for material design changes.

C:

“Maintain traceability from deliverable scope to inspection evidence” addresses recurrence of another problem: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. That problem depends on: This ongoing practice maintains the improvement: Maintain traceability from deliverable scope to inspection evidence. The recurring risk here is: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. The more targeted safeguard is “Require cross-functional impact checks for material design changes” because this ongoing practice maintains the improvement: Require cross-functional impact checks for material design changes.

D:

“Reassess critical-path dates when durations change” addresses recurrence of another problem: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. That problem depends on: This ongoing practice maintains the improvement: Reassess critical-path dates when durations change. The recurring risk here is: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. The more targeted safeguard is “Require cross-functional impact checks for material design changes” because this ongoing practice maintains the improvement: Require cross-functional impact checks for material design changes.

Question 285

In a fictional CAPM project situation, a nonprofit promises a reporting feature in the first release although it depends on data unavailable until a later integration. Which underlying project-management principle best explains the appropriate response?

  1. Roadmaps are most useful when they communicate strategic purpose.
  2. A requested feature does not become a commitment until trade-offs are evaluated.
  3. Release sequencing must respect dependencies, not merely preferred dates.
  4. Roadmaps must respect mandatory prerequisites even when marketing dates are attractive.

Explanation

Correct Answer

C:

The case turns on this distinction: Release sequencing must respect dependencies, not merely preferred dates. Consequently, the targeted action is: Resequence the roadmap so enabling data integration precedes dependent reporting. This reasoning can be checked against: The roadmap visibly links prerequisites and correct release order.

Incorrect Answers

A:

“Roadmaps are most useful when they communicate strategic purpose” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a banking product roadmap has only feature names, obscuring why the investment matters. There the technical reason is: Roadmaps are most useful when they communicate strategic purpose. In this question, the reported issue is: In a fictional CAPM project situation, a nonprofit promises a reporting feature in the first release although it depends on data unavailable until a later integration. The controlling principle is instead: Release sequencing must respect dependencies, not merely preferred dates.

B:

“A requested feature does not become a commitment until trade-offs are evaluated” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a digital archive project has a release slot nearly full and receives another low-priority enhancement request. There the technical reason is: A requested feature does not become a commitment until trade-offs are evaluated. In this question, the reported issue is: In a fictional CAPM project situation, a nonprofit promises a reporting feature in the first release although it depends on data unavailable until a later integration. The controlling principle is instead: Release sequencing must respect dependencies, not merely preferred dates.

D:

“Roadmaps must respect mandatory prerequisites even when marketing dates are attractive” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a retail service product's roadmap lists a loyalty launch before its customer-consent mechanism has regulatory approval. There the technical reason is: Roadmaps must respect mandatory prerequisites even when marketing dates are attractive. In this question, the reported issue is: In a fictional CAPM project situation, a nonprofit promises a reporting feature in the first release although it depends on data unavailable until a later integration. The controlling principle is instead: Release sequencing must respect dependencies, not merely preferred dates.

Question 286

In a fictional CAPM project situation, a warehouse dispatch feature passes demonstrations but fails an agreed offline-recovery scenario. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Include resilience and exception scenarios in each release validation suite.
  2. Include accessibility checks in routine regression tests.
  3. Run release traceability audits against mandatory controls.
  4. Establish explicit stop/go thresholds for safety-critical defects.

Explanation

Correct Answer

A:

This ongoing practice maintains the improvement: Include resilience and exception scenarios in each release validation suite. It follows the targeted action (retest and fix the offline recovery criterion before stakeholder acceptance.) and provides a way to catch recurrence. The underlying principle is: A successful demo does not negate a failed mandatory resilience requirement.

Incorrect Answers

B:

“Include accessibility checks in routine regression tests” addresses recurrence of another problem: In a fictional CAPM project situation, a community portal feature is labeled complete although acceptance tests show keyboard-only navigation fails. That problem depends on: This ongoing practice maintains the improvement: Include accessibility checks in routine regression tests. The recurring risk here is: In a fictional CAPM project situation, a warehouse dispatch feature passes demonstrations but fails an agreed offline-recovery scenario. The more targeted safeguard is “Include resilience and exception scenarios in each release validation suite” because this ongoing practice maintains the improvement: Include resilience and exception scenarios in each release validation suite.

C:

“Run release traceability audits against mandatory controls” addresses recurrence of another problem: In a fictional CAPM project situation, a payment modernization release has all stories marked Done, but one mandated reconciliation requirement has no test result. That problem depends on: This ongoing practice maintains the improvement: Run release traceability audits against mandatory controls. The recurring risk here is: In a fictional CAPM project situation, a warehouse dispatch feature passes demonstrations but fails an agreed offline-recovery scenario. The more targeted safeguard is “Include resilience and exception scenarios in each release validation suite” because this ongoing practice maintains the improvement: Include resilience and exception scenarios in each release validation suite.

D:

“Establish explicit stop/go thresholds for safety-critical defects” addresses recurrence of another problem: In a fictional CAPM project situation, a clinic schedules go-live despite an unresolved high-severity medication data mapping defect. That problem depends on: This ongoing practice maintains the improvement: Establish explicit stop/go thresholds for safety-critical defects. The recurring risk here is: In a fictional CAPM project situation, a warehouse dispatch feature passes demonstrations but fails an agreed offline-recovery scenario. The more targeted safeguard is “Include resilience and exception scenarios in each release validation suite” because this ongoing practice maintains the improvement: Include resilience and exception scenarios in each release validation suite.

Question 287

In a fictional CAPM project situation, a roadworks team has PV $200,000, EV $150,000, and AC $180,000 at a review. Which underlying project-management principle best explains the appropriate response?

  1. The longest path of dependencies, not shortest, determines minimum project duration.
  2. The longest dependent path sets the earliest possible finish when resources are unconstrained.
  3. The project is behind planned value and over the budgeted cost of work performed.
  4. Critical path duration follows the longest start-to-finish dependent sequence.

Explanation

Correct Answer

C:

The case turns on this distinction: The project is behind planned value and over the budgeted cost of work performed. Consequently, the targeted action is: Calculate both SV = −$50,000 and CV = −$30,000 before recommending recovery. This reasoning can be checked against: The report shows EV−PV = −50,000 and EV−AC = −30,000.

Incorrect Answers

A:

“The longest path of dependencies, not shortest, determines minimum project duration” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a pipeline design has task A 2d then B 9d or C 6d, followed by D 3d; a manager assumes the shorter branch controls. There the technical reason is: The longest path of dependencies, not shortest, determines minimum project duration. In this question, the reported issue is: In a fictional CAPM project situation, a roadworks team has PV $200,000, EV $150,000, and AC $180,000 at a review. The controlling principle is instead: The project is behind planned value and over the budgeted cost of work performed.

B:

“The longest dependent path sets the earliest possible finish when resources are unconstrained” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a library renewal schedule has two paths: A 4d then B 6d; A 4d then C 3d; both precede D 2d. There the technical reason is: The longest dependent path sets the earliest possible finish when resources are unconstrained. In this question, the reported issue is: In a fictional CAPM project situation, a roadworks team has PV $200,000, EV $150,000, and AC $180,000 at a review. The controlling principle is instead: The project is behind planned value and over the budgeted cost of work performed.

D:

“Critical path duration follows the longest start-to-finish dependent sequence” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a port upgrade has branch X 5d plus Y 4d and branch X 5d plus Z 7d, joining at final acceptance T 2d. There the technical reason is: Critical path duration follows the longest start-to-finish dependent sequence. In this question, the reported issue is: In a fictional CAPM project situation, a roadworks team has PV $200,000, EV $150,000, and AC $180,000 at a review. The controlling principle is instead: The project is behind planned value and over the budgeted cost of work performed.

Question 288

In a fictional CAPM project situation, a predictive payroll upgrade has a signed requirements baseline and a new late request affecting compliance scope. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Maintain separate change thresholds for compliance and exploratory work.
  2. Establish backlog refinement and demo feedback cadences.
  3. Version baselines and retain impact analysis for each material change.
  4. Verify requirement readiness at each phase gate.

Explanation

Correct Answer

C:

This ongoing practice maintains the improvement: Version baselines and retain impact analysis for each material change. It follows the targeted action (analyze and submit the change for baseline approval before implementation.) and provides a way to catch recurrence. The underlying principle is: Predictive BA maintains approved requirements and formal change traceability.

Incorrect Answers

A:

“Maintain separate change thresholds for compliance and exploratory work” addresses recurrence of another problem: In a fictional CAPM project situation, a hybrid manufacturing project has fixed safety specifications but evolving operator dashboard preferences. That problem depends on: This ongoing practice maintains the improvement: Maintain separate change thresholds for compliance and exploratory work. The recurring risk here is: In a fictional CAPM project situation, a predictive payroll upgrade has a signed requirements baseline and a new late request affecting compliance scope. The more targeted safeguard is “Version baselines and retain impact analysis for each material change” because this ongoing practice maintains the improvement: Version baselines and retain impact analysis for each material change.

B:

“Establish backlog refinement and demo feedback cadences” addresses recurrence of another problem: In a fictional CAPM project situation, a business analyst writes detailed designs alone for an agile team without reviewing user feedback. That problem depends on: This ongoing practice maintains the improvement: Establish backlog refinement and demo feedback cadences. The recurring risk here is: In a fictional CAPM project situation, a predictive payroll upgrade has a signed requirements baseline and a new late request affecting compliance scope. The more targeted safeguard is “Version baselines and retain impact analysis for each material change” because this ongoing practice maintains the improvement: Version baselines and retain impact analysis for each material change.

D:

“Verify requirement readiness at each phase gate” addresses recurrence of another problem: In a fictional CAPM project situation, a predictive infrastructure project has unclear handoff timing for requirements approval before procurement. That problem depends on: This ongoing practice maintains the improvement: Verify requirement readiness at each phase gate. The recurring risk here is: In a fictional CAPM project situation, a predictive payroll upgrade has a signed requirements baseline and a new late request affecting compliance scope. The more targeted safeguard is “Version baselines and retain impact analysis for each material change” because this ongoing practice maintains the improvement: Version baselines and retain impact analysis for each material change.

Question 289

In a fictional CAPM project situation, a local government permit tool has many disconnected requirements and a new accessibility rule with unclear test impact. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The traceability matrix identifies each impacted screen and acceptance test.
  2. Documented journey bottlenecks and validated requirements identify target improvements.
  3. The use case describes normal and alternate flows with observable success criteria.
  4. Stories identify a user, desired outcome, and agreed examples of completion.

Explanation

Correct Answer

A:

The specified evidence tests the exact improvement at issue: The traceability matrix identifies each impacted screen and acceptance test. It supports the chosen response (link the accessibility requirement to affected designs, validation cases, and planned release scope.) rather than merely recording activity. The principle is: Requirements traceability makes cross-cutting change impact visible.

Incorrect Answers

B:

“Documented journey bottlenecks and validated requirements identify target improvements” is evidence for a different source case: In a fictional CAPM project situation, a care provider hears that appointment booking must be faster, but no one defines which users or steps are slow. Its related mechanism is: Unexamined high-level requests are too ambiguous for testable design. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a local government permit tool has many disconnected requirements and a new accessibility rule with unclear test impact. The source-keyed acceptance evidence is “The traceability matrix identifies each impacted screen and acceptance test”.

C:

“The use case describes normal and alternate flows with observable success criteria” is evidence for a different source case: In a fictional CAPM project situation, a travel service needs a login capability and its analysts document only the phrase 'secure login'. Its related mechanism is: Vague slogans do not define testable behavior or exceptions. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a local government permit tool has many disconnected requirements and a new accessibility rule with unclear test impact. The source-keyed acceptance evidence is “The traceability matrix identifies each impacted screen and acceptance test”.

D:

“Stories identify a user, desired outcome, and agreed examples of completion” is evidence for a different source case: In a fictional CAPM project situation, a charity website team has many candidate improvements and needs early user value without full design. Its related mechanism is: User stories can focus incremental dialogue on value instead of prescribing every step. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a local government permit tool has many disconnected requirements and a new accessibility rule with unclear test impact. The source-keyed acceptance evidence is “The traceability matrix identifies each impacted screen and acceptance test”.

Question 290

In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The sprint delivers a testable increment rather than disconnected technical tasks.
  2. Sprint reviews demonstrate finished work and feedback-driven adjustments.
  3. Any agreed backlog change is transparent and leaves a feasible goal.
  4. Dependency records and sprint forecast show achievable ready work.

Explanation

Correct Answer

D:

The specified evidence tests the exact improvement at issue: Dependency records and sprint forecast show achievable ready work. It supports the chosen response (plan an independent vertical slice or address the dependency before committing the blocked feature.) rather than merely recording activity. The principle is: Undisclosed dependencies undermine a credible iteration plan.

Incorrect Answers

A:

“The sprint delivers a testable increment rather than disconnected technical tasks” is evidence for a different source case: In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. Its related mechanism is: Adaptive planning emphasizes small, coherent increments of user value. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The source-keyed acceptance evidence is “Dependency records and sprint forecast show achievable ready work”.

B:

“Sprint reviews demonstrate finished work and feedback-driven adjustments” is evidence for a different source case: In a fictional CAPM project situation, a team uses the percentage of a fixed annual scope completed as the only indicator of adaptive progress. Its related mechanism is: Adaptive progress is better evidenced through usable value than unvalidated activity percentages. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The source-keyed acceptance evidence is “Dependency records and sprint forecast show achievable ready work”.

C:

“Any agreed backlog change is transparent and leaves a feasible goal” is evidence for a different source case: In a fictional CAPM project situation, a product owner announces a new urgent feature mid-sprint and demands that the Sprint Goal stay unchanged without discussion. Its related mechanism is: Sprint scope can be clarified and renegotiated while the Sprint Goal provides focus. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The source-keyed acceptance evidence is “Dependency records and sprint forecast show achievable ready work”.