Question 290
In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: Dependency records and sprint forecast show achievable ready work. It supports the chosen response (plan an independent vertical slice or address the dependency before committing the blocked feature.) rather than merely recording activity. The principle is: Undisclosed dependencies undermine a credible iteration plan.
Incorrect Answers
“The sprint delivers a testable increment rather than disconnected technical tasks” is evidence for a different source case: In a fictional CAPM project situation, a team converts a large predictive WBS into a sprint list by copying every task without user value context. Its related mechanism is: Adaptive planning emphasizes small, coherent increments of user value. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The source-keyed acceptance evidence is “Dependency records and sprint forecast show achievable ready work”.
“Sprint reviews demonstrate finished work and feedback-driven adjustments” is evidence for a different source case: In a fictional CAPM project situation, a team uses the percentage of a fixed annual scope completed as the only indicator of adaptive progress. Its related mechanism is: Adaptive progress is better evidenced through usable value than unvalidated activity percentages. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The source-keyed acceptance evidence is “Dependency records and sprint forecast show achievable ready work”.
“Any agreed backlog change is transparent and leaves a feasible goal” is evidence for a different source case: In a fictional CAPM project situation, a product owner announces a new urgent feature mid-sprint and demands that the Sprint Goal stay unchanged without discussion. Its related mechanism is: Sprint scope can be clarified and renegotiated while the Sprint Goal provides focus. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a museum portal feature depends on an identity interface owned by a separate team that will not be ready next sprint. The source-keyed acceptance evidence is “Dependency records and sprint forecast show achievable ready work”.