Question 420
In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: The change record aligns drawings, budget, procurement, schedule, and acceptance. It supports the chosen response (evaluate the change across integrated plans before approval and implementation.) rather than merely recording activity. The principle is: Integration management keeps plan components internally consistent.
Incorrect Answers
“Network and schedule show test predecessor links and acceptance completion” is evidence for a different source case: In a fictional CAPM project situation, a rail signaling project has three activities dependent on a single final software test, but the test is absent from its network. Its related mechanism is: Omitted dependencies create an artificially early finish forecast. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. The source-keyed acceptance evidence is “The change record aligns drawings, budget, procurement, schedule, and acceptance”.
“Inspection records show acceptance of each deliverable package” is evidence for a different source case: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. Its related mechanism is: Estimating work alone does not establish verified completion. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. The source-keyed acceptance evidence is “The change record aligns drawings, budget, procurement, schedule, and acceptance”.
“The long path totals 3+8+4=15 days; the other totals 3+5+4=12” is evidence for a different source case: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. Its related mechanism is: The longest dependent route controls completion in an unconstrained network. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. The source-keyed acceptance evidence is “The change record aligns drawings, budget, procurement, schedule, and acceptance”.