Question 400
In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: Predictive work depends on controlled prerequisites to limit expensive downstream changes. Consequently, the targeted action is: Complete required design and authorization processes before field construction. This reasoning can be checked against: A signed design package and permit checklist precede mobilization.
Incorrect Answers
“Matrix structures split resource authority, so formal coordination is needed” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a matrix organization lends mechanical engineers to two simultaneous capital projects without resource commitments. There the technical reason is: Matrix structures split resource authority, so formal coordination is needed. In this question, the reported issue is: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. The controlling principle is instead: Predictive work depends on controlled prerequisites to limit expensive downstream changes.
“A predictive implementation relies on planned sequencing and demonstrable acceptance” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, an airport baggage replacement has strict acceptance test sequences but the team uses an unordered feature wish list. There the technical reason is: A predictive implementation relies on planned sequencing and demonstrable acceptance. In this question, the reported issue is: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. The controlling principle is instead: Predictive work depends on controlled prerequisites to limit expensive downstream changes.
“Project components represent different outcomes and must not be conflated” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a municipal bridge program treats delivery of approved drawings as equivalent to completed construction. There the technical reason is: Project components represent different outcomes and must not be conflated. In this question, the reported issue is: In a fictional CAPM project situation, a public-works contractor starts construction before the approved detailed design has passed technical review. The controlling principle is instead: Predictive work depends on controlled prerequisites to limit expensive downstream changes.