Question 390
In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: The long path totals 3+8+4=15 days; the other totals 3+5+4=12. It supports the chosen response (set the earliest network completion at 15 days along P-Q-S.) rather than merely recording activity. The principle is: The longest dependent route controls completion in an unconstrained network.
Incorrect Answers
“SPI equals 0.70 using the same effort-value units” is evidence for a different source case: In a fictional CAPM project situation, a campus lighting installation plans 90 days of effort value by the checkpoint but has earned only 63 equivalent days. Its related mechanism is: Earned work is only 70% of planned work in earned-value terms. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. The source-keyed acceptance evidence is “The long path totals 3+8+4=15 days; the other totals 3+5+4=12”.
“The cost variance report shows positive $5,000” is evidence for a different source case: In a fictional CAPM project situation, a research laboratory has $55,000 earned value and $50,000 actual cost at the same data date. Its related mechanism is: The team earned more budgeted value than it spent, absent quality or scope omissions. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. The source-keyed acceptance evidence is “The long path totals 3+8+4=15 days; the other totals 3+5+4=12”.
“The report shows EV−PV = −50,000 and EV−AC = −30,000” is evidence for a different source case: In a fictional CAPM project situation, a roadworks team has PV $200,000, EV $150,000, and AC $180,000 at a review. Its related mechanism is: The project is behind planned value and over the budgeted cost of work performed. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. The source-keyed acceptance evidence is “The long path totals 3+8+4=15 days; the other totals 3+5+4=12”.