Question 370
In a fictional CAPM project situation, a finance director asks for a one-page investment summary, but the analyst sends raw test-case spreadsheets. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: Executive communication should foreground decisions and implications. Consequently, the targeted action is: Provide a concise decision-oriented summary of benefits, risks, and material trade-offs. This reasoning can be checked against: The director can identify the decision and supporting evidence without raw-detail overload.
Incorrect Answers
“Requirements information must reach every role whose work or decision it changes” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a field-service analyst learns a critical safety requirement but informs only the software developers. There the technical reason is: Requirements information must reach every role whose work or decision it changes. In this question, the reported issue is: In a fictional CAPM project situation, a finance director asks for a one-page investment summary, but the analyst sends raw test-case spreadsheets. The controlling principle is instead: Executive communication should foreground decisions and implications.
“Uncontrolled communication creates inconsistent acceptance expectations” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a team announces changed acceptance criteria during a release call without telling customer testers in advance. There the technical reason is: Uncontrolled communication creates inconsistent acceptance expectations. In this question, the reported issue is: In a fictional CAPM project situation, a finance director asks for a one-page investment summary, but the analyst sends raw test-case spreadsheets. The controlling principle is instead: Executive communication should foreground decisions and implications.
“Communication media should be proportionate to complexity and urgency” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a remote engineering team uses lengthy meetings to resolve simple status questions across time zones. There the technical reason is: Communication media should be proportionate to complexity and urgency. In this question, the reported issue is: In a fictional CAPM project situation, a finance director asks for a one-page investment summary, but the analyst sends raw test-case spreadsheets. The controlling principle is instead: Executive communication should foreground decisions and implications.