Question 500
In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: Load-test reports show response time under the agreed demand profile. It supports the chosen response (evaluate performance against the nonfunctional acceptance requirement and defer approval if breached.) rather than merely recording activity. The principle is: Functional completion cannot replace nonfunctional acceptance evidence.
Incorrect Answers
“Every mandatory alert requirement maps to a passing verification artifact” is evidence for a different source case: In a fictional CAPM project situation, a public safety dispatch product has traceability for 95% of requirements while five mandatory alerts are untested. Its related mechanism is: High completion percentages cannot waive specific critical requirements. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. The source-keyed acceptance evidence is “Load-test reports show response time under the agreed demand profile”.
“Acceptance evidence shows the system resumes correctly after connectivity restoration” is evidence for a different source case: In a fictional CAPM project situation, a warehouse dispatch feature passes demonstrations but fails an agreed offline-recovery scenario. Its related mechanism is: A successful demo does not negate a failed mandatory resilience requirement. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. The source-keyed acceptance evidence is “Load-test reports show response time under the agreed demand profile”.
“The acceptance report documents keyboard navigation results and disposition” is evidence for a different source case: In a fictional CAPM project situation, a community portal feature is labeled complete although acceptance tests show keyboard-only navigation fails. Its related mechanism is: Acceptance depends on meeting agreed criteria, not development status alone. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a cargo booking system passes functional tests but misses its agreed response-time threshold under peak load. The source-keyed acceptance evidence is “Load-test reports show response time under the agreed demand profile”.