Question 520
In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. Which action most directly addresses the problem while respecting the relevant roles and constraints?
Explanation
Correct Answer
This directly addresses the case's governing problem: Apply the quality plan's inspection and corrective-action procedure before signoff. The key reason is that conformance must be demonstrated against requirements, not presumed from installation. A suitable completion check is: Retest results meet the specified pressure threshold with defect closure evidence.
Incorrect Answers
“Evaluate the change across integrated plans before approval and implementation” responds to another technical or business failure: In a fictional CAPM project situation, a data-center project updates a design drawing but not the cost baseline or procurement order. That source case depends on: Integration management keeps plan components internally consistent. The present issue is: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. The more direct action is “Apply the quality plan's inspection and corrective-action procedure before signoff” because conformance must be demonstrated against requirements, not presumed from installation.
“Add the integration test as a dependent activity before final acceptance” responds to another technical or business failure: In a fictional CAPM project situation, a rail signaling project has three activities dependent on a single final software test, but the test is absent from its network. That source case depends on: Omitted dependencies create an artificially early finish forecast. The present issue is: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. The more direct action is “Apply the quality plan's inspection and corrective-action procedure before signoff” because conformance must be demonstrated against requirements, not presumed from installation.
“Link the WBS work packages to defined quality and completion criteria” responds to another technical or business failure: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. That source case depends on: Estimating work alone does not establish verified completion. The present issue is: In a fictional CAPM project situation, a wastewater upgrade finds failed pressure tests after piping installation. The more direct action is “Apply the quality plan's inspection and corrective-action procedure before signoff” because conformance must be demonstrated against requirements, not presumed from installation.