McAfee Secure

PMI CAPM Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Training Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Training Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 62

Question 610

In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. Which underlying project-management principle best explains the appropriate response?

  1. Effective communication must suit stakeholder language and information needs.
  2. Benefits do not materialize merely because a feature is installed.
  3. A predefined response should be activated when its monitored trigger occurs.
  4. A vague contingency cannot be applied consistently under pressure.

Explanation

Correct Answer

D:

The case turns on this distinction: A vague contingency cannot be applied consistently under pressure. Consequently, the targeted action is: Define observable trigger criteria and make the response executable. This reasoning can be checked against: Risk records include measurable thresholds, response owner, and activation steps.

Incorrect Answers

A:

“Effective communication must suit stakeholder language and information needs” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a communications plan requires accessible summaries, yet a team shares only technical diagrams with community representatives. There the technical reason is: Effective communication must suit stakeholder language and information needs. In this question, the reported issue is: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The controlling principle is instead: A vague contingency cannot be applied consistently under pressure.

B:

“Benefits do not materialize merely because a feature is installed” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a sponsor expected reduced staff overtime after a new scheduling tool, but the benefit metric was never assigned. There the technical reason is: Benefits do not materialize merely because a feature is installed. In this question, the reported issue is: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The controlling principle is instead: A vague contingency cannot be applied consistently under pressure.

C:

“A predefined response should be activated when its monitored trigger occurs” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. There the technical reason is: A predefined response should be activated when its monitored trigger occurs. In this question, the reported issue is: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The controlling principle is instead: A vague contingency cannot be applied consistently under pressure.

Question 611

In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. What evidence would most directly demonstrate that the appropriate response was effective?

  1. Risk records include measurable thresholds, response owner, and activation steps.
  2. Stakeholders confirm understanding and the distribution log records delivery.
  3. The benefits register links an owner, baseline, target, and reporting schedule.
  4. Defect metrics meet the trigger and approved response actions are recorded.

Explanation

Correct Answer

A:

The specified evidence tests the exact improvement at issue: Risk records include measurable thresholds, response owner, and activation steps. It supports the chosen response (define observable trigger criteria and make the response executable.) rather than merely recording activity. The principle is: A vague contingency cannot be applied consistently under pressure.

Incorrect Answers

B:

“Stakeholders confirm understanding and the distribution log records delivery” is evidence for a different source case: In a fictional CAPM project situation, a communications plan requires accessible summaries, yet a team shares only technical diagrams with community representatives. Its related mechanism is: Effective communication must suit stakeholder language and information needs. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The source-keyed acceptance evidence is “Risk records include measurable thresholds, response owner, and activation steps”.

C:

“The benefits register links an owner, baseline, target, and reporting schedule” is evidence for a different source case: In a fictional CAPM project situation, a sponsor expected reduced staff overtime after a new scheduling tool, but the benefit metric was never assigned. Its related mechanism is: Benefits do not materialize merely because a feature is installed. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The source-keyed acceptance evidence is “Risk records include measurable thresholds, response owner, and activation steps”.

D:

“Defect metrics meet the trigger and approved response actions are recorded” is evidence for a different source case: In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. Its related mechanism is: A predefined response should be activated when its monitored trigger occurs. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The source-keyed acceptance evidence is “Risk records include measurable thresholds, response owner, and activation steps”.

Question 612

In a fictional CAPM project situation, a team proposes adding a mobile app to a water-meter project whose approved scope covers only sensor installation. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Record the intended waiting-time benefit and how it will be measured after delivery.
  2. Treat the platform migration as temporary change work distinct from monthly operations.
  3. Define a temporary launch project and transition the recurring moderation service to operational management.
  4. Assess the proposed mobile app against objectives and route any scope expansion for approval.

Explanation

Correct Answer

D:

This directly addresses the case's governing problem: Assess the proposed mobile app against objectives and route any scope expansion for approval. The key reason is that an attractive feature is not automatically within the authorized project scope. A suitable completion check is: The scope baseline and change decision show whether the app is included and funded.

Incorrect Answers

A:

“Record the intended waiting-time benefit and how it will be measured after delivery” responds to another technical or business failure: In a fictional CAPM project situation, a hospital redesign aims to shorten patient waiting time but its charter only mentions installing kiosks. That source case depends on: Delivering kiosks is an output; shorter waits are an outcome requiring validation. The present issue is: In a fictional CAPM project situation, a team proposes adding a mobile app to a water-meter project whose approved scope covers only sensor installation. The more direct action is “Assess the proposed mobile app against objectives and route any scope expansion for approval” because an attractive feature is not automatically within the authorized project scope.

B:

“Treat the platform migration as temporary change work distinct from monthly operations” responds to another technical or business failure: In a fictional CAPM project situation, a research group has a recurring monthly reporting routine and a one-time migration to a new reporting platform. That source case depends on: Routine repetitive production is operational, while a one-time platform change is a project. The present issue is: In a fictional CAPM project situation, a team proposes adding a mobile app to a water-meter project whose approved scope covers only sensor installation. The more direct action is “Assess the proposed mobile app against objectives and route any scope expansion for approval” because an attractive feature is not automatically within the authorized project scope.

C:

“Define a temporary launch project and transition the recurring moderation service to operational management” responds to another technical or business failure: In a fictional CAPM project situation, a digital publishing company wants to establish an indefinite content moderation service and calls the staffing launch a permanent project. That source case depends on: Establishing a capability is temporary project work; operating it indefinitely is ongoing activity. The present issue is: In a fictional CAPM project situation, a team proposes adding a mobile app to a water-meter project whose approved scope covers only sensor installation. The more direct action is “Assess the proposed mobile app against objectives and route any scope expansion for approval” because an attractive feature is not automatically within the authorized project scope.

Question 613

In a fictional CAPM project situation, a government service product has unstable user needs but its contract fixes every feature detail upfront. Which action most directly addresses the problem while respecting the relevant roles and constraints?

  1. Use an adaptive flow-based approach with explicit priority and work-in-progress limits.
  2. Run short experiments with representative users and adapt priorities from measured outcomes.
  3. Explore a managed adaptive arrangement with staged outcomes and transparent reprioritization.
  4. Adopt short adaptive delivery cycles and re-order work using validated feedback.

Explanation

Correct Answer

C:

This directly addresses the case's governing problem: Explore a managed adaptive arrangement with staged outcomes and transparent reprioritization. The key reason is that uncertain requirements fit shorter feedback cycles when governance allows them. A suitable completion check is: Incremental acceptance records show useful value and controlled constraints.

Incorrect Answers

A:

“Use an adaptive flow-based approach with explicit priority and work-in-progress limits” responds to another technical or business failure: In a fictional CAPM project situation, a mature maintenance team has repetitive urgent tickets arriving continuously, and sprint commitment frequently collapses. That source case depends on: Interrupt-driven work may be managed better through flow than fixed batches. The present issue is: In a fictional CAPM project situation, a government service product has unstable user needs but its contract fixes every feature detail upfront. The more direct action is “Explore a managed adaptive arrangement with staged outcomes and transparent reprioritization” because uncertain requirements fit shorter feedback cycles when governance allows them.

B:

“Run short experiments with representative users and adapt priorities from measured outcomes” responds to another technical or business failure: In a fictional CAPM project situation, a new analytics product has divergent user expectations and no reliable evidence that a fixed specification would satisfy them. That source case depends on: Exploratory product uncertainty favors iterative learning over rigid full-detail plans. The present issue is: In a fictional CAPM project situation, a government service product has unstable user needs but its contract fixes every feature detail upfront. The more direct action is “Explore a managed adaptive arrangement with staged outcomes and transparent reprioritization” because uncertain requirements fit shorter feedback cycles when governance allows them.

D:

“Adopt short adaptive delivery cycles and re-order work using validated feedback” responds to another technical or business failure: In a fictional CAPM project situation, a travel app team receives weekly consumer feedback that overturns original feature priorities. That source case depends on: High product uncertainty benefits from learning through repeated delivery. The present issue is: In a fictional CAPM project situation, a government service product has unstable user needs but its contract fixes every feature detail upfront. The more direct action is “Explore a managed adaptive arrangement with staged outcomes and transparent reprioritization” because uncertain requirements fit shorter feedback cycles when governance allows them.

Question 614

In a fictional CAPM project situation, a Scrum team meets at sprint end only to assign blame for defects. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Limit improvements to actionable experiments with owners and follow-up.
  2. Tune WIP limits using observed cycle time and capacity.
  3. Keep test coverage and build health visible to developers.
  4. Review integration dependencies and product-level priorities regularly.

Explanation

Correct Answer

A:

This ongoing practice maintains the improvement: Limit improvements to actionable experiments with owners and follow-up. It follows the targeted action (hold a retrospective to identify process improvements and concrete experiments.) and provides a way to catch recurrence. The underlying principle is: The retrospective examines team effectiveness rather than proving product acceptance.

Incorrect Answers

B:

“Tune WIP limits using observed cycle time and capacity” addresses recurrence of another problem: In a fictional CAPM project situation, a Kanban repair team starts ten new tickets while older ones stay blocked. That problem depends on: This ongoing practice maintains the improvement: Tune WIP limits using observed cycle time and capacity. The recurring risk here is: In a fictional CAPM project situation, a Scrum team meets at sprint end only to assign blame for defects. The more targeted safeguard is “Limit improvements to actionable experiments with owners and follow-up” because this ongoing practice maintains the improvement: Limit improvements to actionable experiments with owners and follow-up.

C:

“Keep test coverage and build health visible to developers” addresses recurrence of another problem: In a fictional CAPM project situation, an XP-focused development team merges code without automated tests and finds regressions each week. That problem depends on: This ongoing practice maintains the improvement: Keep test coverage and build health visible to developers. The recurring risk here is: In a fictional CAPM project situation, a Scrum team meets at sprint end only to assign blame for defects. The more targeted safeguard is “Limit improvements to actionable experiments with owners and follow-up” because this ongoing practice maintains the improvement: Limit improvements to actionable experiments with owners and follow-up.

D:

“Review integration dependencies and product-level priorities regularly” addresses recurrence of another problem: In a fictional CAPM project situation, two Scrum teams work on one product but maintain conflicting product goals and prioritization. That problem depends on: This ongoing practice maintains the improvement: Review integration dependencies and product-level priorities regularly. The recurring risk here is: In a fictional CAPM project situation, a Scrum team meets at sprint end only to assign blame for defects. The more targeted safeguard is “Limit improvements to actionable experiments with owners and follow-up” because this ongoing practice maintains the improvement: Limit improvements to actionable experiments with owners and follow-up.

Question 615

In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The long path totals 3+8+4=15 days; the other totals 3+5+4=12.
  2. SPI equals 0.70 using the same effort-value units.
  3. Inspection records show acceptance of each deliverable package.
  4. The cost variance report shows positive $5,000.

Explanation

Correct Answer

C:

The specified evidence tests the exact improvement at issue: Inspection records show acceptance of each deliverable package. It supports the chosen response (link the WBS work packages to defined quality and completion criteria.) rather than merely recording activity. The principle is: Estimating work alone does not establish verified completion.

Incorrect Answers

A:

“The long path totals 3+8+4=15 days; the other totals 3+5+4=12” is evidence for a different source case: In a fictional CAPM project situation, an archive migration has two parallel paths: P 3d then Q 8d; P 3d then R 5d; both require S 4d. Its related mechanism is: The longest dependent route controls completion in an unconstrained network. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. The source-keyed acceptance evidence is “Inspection records show acceptance of each deliverable package”.

B:

“SPI equals 0.70 using the same effort-value units” is evidence for a different source case: In a fictional CAPM project situation, a campus lighting installation plans 90 days of effort value by the checkpoint but has earned only 63 equivalent days. Its related mechanism is: Earned work is only 70% of planned work in earned-value terms. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. The source-keyed acceptance evidence is “Inspection records show acceptance of each deliverable package”.

D:

“The cost variance report shows positive $5,000” is evidence for a different source case: In a fictional CAPM project situation, a research laboratory has $55,000 earned value and $50,000 actual cost at the same data date. Its related mechanism is: The team earned more budgeted value than it spent, absent quality or scope omissions. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a food-storage build uses estimated task durations but no formal scope acceptance thresholds. The source-keyed acceptance evidence is “Inspection records show acceptance of each deliverable package”.

Question 616

In a fictional CAPM project situation, a matrix organization lends mechanical engineers to two simultaneous capital projects without resource commitments. Which underlying project-management principle best explains the appropriate response?

  1. A predictive implementation relies on planned sequencing and demonstrable acceptance.
  2. Project components represent different outcomes and must not be conflated.
  3. Matrix structures split resource authority, so formal coordination is needed.
  4. High retooling cost favors early requirements confirmation and formal change control.

Explanation

Correct Answer

C:

The case turns on this distinction: Matrix structures split resource authority, so formal coordination is needed. Consequently, the targeted action is: Negotiate and confirm shared specialist availability in the predictive resource plan. This reasoning can be checked against: A resource allocation agreement aligns functional managers and milestones.

Incorrect Answers

A:

“A predictive implementation relies on planned sequencing and demonstrable acceptance” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, an airport baggage replacement has strict acceptance test sequences but the team uses an unordered feature wish list. There the technical reason is: A predictive implementation relies on planned sequencing and demonstrable acceptance. In this question, the reported issue is: In a fictional CAPM project situation, a matrix organization lends mechanical engineers to two simultaneous capital projects without resource commitments. The controlling principle is instead: Matrix structures split resource authority, so formal coordination is needed.

B:

“Project components represent different outcomes and must not be conflated” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a municipal bridge program treats delivery of approved drawings as equivalent to completed construction. There the technical reason is: Project components represent different outcomes and must not be conflated. In this question, the reported issue is: In a fictional CAPM project situation, a matrix organization lends mechanical engineers to two simultaneous capital projects without resource commitments. The controlling principle is instead: Matrix structures split resource authority, so formal coordination is needed.

D:

“High retooling cost favors early requirements confirmation and formal change control” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, an aerospace supplier receives approved tolerances that cannot change after tooling is produced. There the technical reason is: High retooling cost favors early requirements confirmation and formal change control. In this question, the reported issue is: In a fictional CAPM project situation, a matrix organization lends mechanical engineers to two simultaneous capital projects without resource commitments. The controlling principle is instead: Matrix structures split resource authority, so formal coordination is needed.

Question 617

In a fictional CAPM project situation, a city data analyst marks an uncertain vendor API outage as already resolved because the last integration test passed. Which continuing control would most directly reduce the chance of this problem recurring?

  1. Use gift disclosures and independent evaluation oversight.
  2. Assign a transition owner and move postlaunch service work to operational governance.
  3. Monitor dependency health and rehearse fallback integration procedures.
  4. Maintain a program dependency map and shared benefits tracking.

Explanation

Correct Answer

C:

This ongoing practice maintains the improvement: Monitor dependency health and rehearse fallback integration procedures. It follows the targeted action (treat the possible future API outage as a risk and assess probability, impact, and response.) and provides a way to catch recurrence. The underlying principle is: A successful test does not eliminate uncertain future exposure.

Incorrect Answers

A:

“Use gift disclosures and independent evaluation oversight” addresses recurrence of another problem: In a fictional CAPM project situation, a vendor offers a coordinator a gift immediately before supplier evaluation scores are finalized. That problem depends on: This ongoing practice maintains the improvement: Use gift disclosures and independent evaluation oversight. The recurring risk here is: In a fictional CAPM project situation, a city data analyst marks an uncertain vendor API outage as already resolved because the last integration test passed. The more targeted safeguard is “Monitor dependency health and rehearse fallback integration procedures” because this ongoing practice maintains the improvement: Monitor dependency health and rehearse fallback integration procedures.

B:

“Assign a transition owner and move postlaunch service work to operational governance” addresses recurrence of another problem: In a fictional CAPM project situation, a town transit authority is building a new ticketing system while separately running daily ticket support; leadership calls both efforts projects. That problem depends on: This ongoing practice maintains the improvement: Assign a transition owner and move postlaunch service work to operational governance. The recurring risk here is: In a fictional CAPM project situation, a city data analyst marks an uncertain vendor API outage as already resolved because the last integration test passed. The more targeted safeguard is “Monitor dependency health and rehearse fallback integration procedures” because this ongoing practice maintains the improvement: Monitor dependency health and rehearse fallback integration procedures.

D:

“Maintain a program dependency map and shared benefits tracking” addresses recurrence of another problem: In a fictional CAPM project situation, a health network is coordinating a shared electronic-record program containing several interdependent hospital migrations. That problem depends on: This ongoing practice maintains the improvement: Maintain a program dependency map and shared benefits tracking. The recurring risk here is: In a fictional CAPM project situation, a city data analyst marks an uncertain vendor API outage as already resolved because the last integration test passed. The more targeted safeguard is “Monitor dependency health and rehearse fallback integration procedures” because this ongoing practice maintains the improvement: Monitor dependency health and rehearse fallback integration procedures.

Question 618

In a fictional CAPM project situation, a robotics group has an untested human-interface concept and wants to freeze all interactions for a year. What evidence would most directly demonstrate that the appropriate response was effective?

  1. Prototype tests reveal which interactions succeed before large commitments.
  2. Accessible board data and review notes show aligned priorities and blockers.
  3. Deployment records and stakeholder demos show frequent usable results.
  4. Incremental acceptance records show useful value and controlled constraints.

Explanation

Correct Answer

A:

The specified evidence tests the exact improvement at issue: Prototype tests reveal which interactions succeed before large commitments. It supports the chosen response (build a thin prototype and inspect real-user feedback before fixing detailed design.) rather than merely recording activity. The principle is: Adaptive methods reduce uncertainty through short feedback loops.

Incorrect Answers

B:

“Accessible board data and review notes show aligned priorities and blockers” is evidence for a different source case: In a fictional CAPM project situation, a virtual software team lacks a reliable shared board or frequent feedback from its product representative. Its related mechanism is: Adaptive work needs visibility and timely collaboration regardless of location. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a robotics group has an untested human-interface concept and wants to freeze all interactions for a year. The source-keyed acceptance evidence is “Prototype tests reveal which interactions succeed before large commitments”.

C:

“Deployment records and stakeholder demos show frequent usable results” is evidence for a different source case: In a fictional CAPM project situation, a research team has safe deployment automation but waits six months to show working software. Its related mechanism is: Automation and engaged stakeholders are assets that support adaptive flow. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a robotics group has an untested human-interface concept and wants to freeze all interactions for a year. The source-keyed acceptance evidence is “Prototype tests reveal which interactions succeed before large commitments”.

D:

“Incremental acceptance records show useful value and controlled constraints” is evidence for a different source case: In a fictional CAPM project situation, a government service product has unstable user needs but its contract fixes every feature detail upfront. Its related mechanism is: Uncertain requirements fit shorter feedback cycles when governance allows them. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a robotics group has an untested human-interface concept and wants to freeze all interactions for a year. The source-keyed acceptance evidence is “Prototype tests reveal which interactions succeed before large commitments”.

Question 619

In a fictional CAPM project situation, a wind-farm project fails a contract inspection but its acceptance log marks the milestone complete. Which underlying project-management principle best explains the appropriate response?

  1. Variances are meaningful only relative to an agreed reference point.
  2. Evidence-based controls must override optimistic progress claims.
  3. Uncontrolled change history obscures scope and cost accountability.
  4. Cost efficiency alone does not certify delivered scope or required quality.

Explanation

Correct Answer

B:

The case turns on this distinction: Evidence-based controls must override optimistic progress claims. Consequently, the targeted action is: Withhold acceptance until the specified inspection criteria are met and recorded. This reasoning can be checked against: A signed inspection certificate supports the accepted milestone.

Incorrect Answers

A:

“Variances are meaningful only relative to an agreed reference point” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a rail project collects schedule delays but omits the current approved baseline from status reports. There the technical reason is: Variances are meaningful only relative to an agreed reference point. In this question, the reported issue is: In a fictional CAPM project situation, a wind-farm project fails a contract inspection but its acceptance log marks the milestone complete. The controlling principle is instead: Evidence-based controls must override optimistic progress claims.

C:

“Uncontrolled change history obscures scope and cost accountability” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a warehouse expansion has no consistent record of approved site-scope changes. There the technical reason is: Uncontrolled change history obscures scope and cost accountability. In this question, the reported issue is: In a fictional CAPM project situation, a wind-farm project fails a contract inspection but its acceptance log marks the milestone complete. The controlling principle is instead: Evidence-based controls must override optimistic progress claims.

D:

“Cost efficiency alone does not certify delivered scope or required quality” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, an engineering manager reports a favorable cost index but ignores rework due to failed acceptance tests. There the technical reason is: Cost efficiency alone does not certify delivered scope or required quality. In this question, the reported issue is: In a fictional CAPM project situation, a wind-farm project fails a contract inspection but its acceptance log marks the milestone complete. The controlling principle is instead: Evidence-based controls must override optimistic progress claims.

Question 620

In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. What evidence would most directly demonstrate that the appropriate response was effective?

  1. The performance report shows negative $20,000 cost variance.
  2. The earned-value report shows SV of negative $20,000.
  3. Schedule performance index equals 0.90 at the status date.
  4. Cost performance index equals 1.20 at the reporting cutoff.

Explanation

Correct Answer

B:

The specified evidence tests the exact improvement at issue: The earned-value report shows SV of negative $20,000. It supports the chosen response (report schedule variance SV = EV − PV = −$20,000 and evaluate recovery options.) rather than merely recording activity. The principle is: Earned value below planned value indicates less budgeted work achieved than scheduled.

Incorrect Answers

A:

“The performance report shows negative $20,000 cost variance” is evidence for a different source case: In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. Its related mechanism is: Actual cost exceeds the budgeted value of work performed, indicating overrun. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. The source-keyed acceptance evidence is “The earned-value report shows SV of negative $20,000”.

C:

“Schedule performance index equals 0.90 at the status date” is evidence for a different source case: In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. Its related mechanism is: An SPI below 1 signals that earned value trails scheduled value. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. The source-keyed acceptance evidence is “The earned-value report shows SV of negative $20,000”.

D:

“Cost performance index equals 1.20 at the reporting cutoff” is evidence for a different source case: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. Its related mechanism is: A CPI above 1 means more budgeted value earned per unit of actual cost. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. The source-keyed acceptance evidence is “The earned-value report shows SV of negative $20,000”.