Question 610
In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. Which underlying project-management principle best explains the appropriate response?
Explanation
Correct Answer
The case turns on this distinction: A vague contingency cannot be applied consistently under pressure. Consequently, the targeted action is: Define observable trigger criteria and make the response executable. This reasoning can be checked against: Risk records include measurable thresholds, response owner, and activation steps.
Incorrect Answers
“Effective communication must suit stakeholder language and information needs” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a communications plan requires accessible summaries, yet a team shares only technical diagrams with community representatives. There the technical reason is: Effective communication must suit stakeholder language and information needs. In this question, the reported issue is: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The controlling principle is instead: A vague contingency cannot be applied consistently under pressure.
“Benefits do not materialize merely because a feature is installed” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a sponsor expected reduced staff overtime after a new scheduling tool, but the benefit metric was never assigned. There the technical reason is: Benefits do not materialize merely because a feature is installed. In this question, the reported issue is: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The controlling principle is instead: A vague contingency cannot be applied consistently under pressure.
“A predefined response should be activated when its monitored trigger occurs” describes the principle relevant to this other source scenario: In a fictional CAPM project situation, a risk response plan says to switch suppliers if defect rates exceed 4%, and rates reach 6%. There the technical reason is: A predefined response should be activated when its monitored trigger occurs. In this question, the reported issue is: In a fictional CAPM project situation, a logistics project lists a high-impact delay risk and assigns a workaround but omits a trigger. The controlling principle is instead: A vague contingency cannot be applied consistently under pressure.