Question 620
In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. What evidence would most directly demonstrate that the appropriate response was effective?
Explanation
Correct Answer
The specified evidence tests the exact improvement at issue: The earned-value report shows SV of negative $20,000. It supports the chosen response (report schedule variance SV = EV − PV = −$20,000 and evaluate recovery options.) rather than merely recording activity. The principle is: Earned value below planned value indicates less budgeted work achieved than scheduled.
Incorrect Answers
“The performance report shows negative $20,000 cost variance” is evidence for a different source case: In a fictional CAPM project situation, a hospital installation has earned value $90,000 and actual cost $110,000 to date. Its related mechanism is: Actual cost exceeds the budgeted value of work performed, indicating overrun. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. The source-keyed acceptance evidence is “The earned-value report shows SV of negative $20,000”.
“Schedule performance index equals 0.90 at the status date” is evidence for a different source case: In a fictional CAPM project situation, a school modernization has earned value $72,000 against planned value $80,000. Its related mechanism is: An SPI below 1 signals that earned value trails scheduled value. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. The source-keyed acceptance evidence is “The earned-value report shows SV of negative $20,000”.
“Cost performance index equals 1.20 at the reporting cutoff” is evidence for a different source case: In a fictional CAPM project situation, a facilities renewal has earned value $84,000 and actual cost $70,000. Its related mechanism is: A CPI above 1 means more budgeted value earned per unit of actual cost. That observation would not directly verify this question’s condition: In a fictional CAPM project situation, a renewal project planned value is $120,000 and earned value is $100,000 at the checkpoint. The source-keyed acceptance evidence is “The earned-value report shows SV of negative $20,000”.