Question 1
A regional permit portal project faces a forty-percent hosting cost increase after supplier selection; the projected benefits have not changed, yet the manager proposes proceeding without revisiting viability. What change would best align the project with the relevant PRINCE2 guidance?
Explanation
Correct Answer
This response is justified because continued business justification is a live decision throughout the project rather than a one-time endorsement of the original proposal. Reassess costs, benefits and risks in the business case, and seek a decision on continued justification before committing further funds. The response can be checked against delivery evidence: a refreshed business case and an authorized continuation decision show that the revised investment still offers an acceptable balance of value and risk.
Incorrect Answers
Focus on defined product acceptance concerns a different project control. It could help in a project where that condition applies, but it does not directly correct the present situation: A regional permit portal project faces a forty-percent hosting cost increase after supplier selection Here, reassess costs, benefits and risks in the business case, and seek a decision on continued justification before committing further funds. The reason is that continued business justification is a live decision throughout the project rather than a one-time endorsement of the original proposal.
Use lessons from a prior project concerns a different project control. Here, reassess costs, benefits and risks in the business case, and seek a decision on continued justification before committing further funds. The reason is that continued business justification is a live decision throughout the project rather than a one-time endorsement of the original proposal.
Escalate forecast tolerance breach concerns a different project control. Here, reassess costs, benefits and risks in the business case, and seek a decision on continued justification before committing further funds. The reason is that continued business justification is a live decision throughout the project rather than a one-time endorsement of the original proposal.