Question 10
A hospital scheduling project discovers the regulatory change it was built to satisfy has been cancelled, but its team argues that completing the software will protect sunk expenditure. What underlying management principle most directly explains the concern?
Explanation
Correct Answer
The important PRINCE2 distinction is that money already spent is not a reason to continue when the remaining expenditure no longer supports sufficient future benefits or strategic value. That reasoning makes the targeted action appropriate: escalate the loss of value to the project board and recommend stopping or materially reshaping work if continued justification cannot be established. The described project conditions show why the distinction matters: A hospital scheduling project discovers the regulatory change it was built to satisfy has been cancelled, but its team argues that completing the software will protect sunk expenditure.
Incorrect Answers
Focus on defined product acceptance describes a different management issue. The relevant cause instead is that money already spent is not a reason to continue when the remaining expenditure no longer supports sufficient future benefits or strategic value.
Escalate forecast tolerance breach describes a different management issue. The relevant cause instead is that money already spent is not a reason to continue when the remaining expenditure no longer supports sufficient future benefits or strategic value.
Separate assurance from delivery describes a different management issue. The relevant cause instead is that money already spent is not a reason to continue when the remaining expenditure no longer supports sufficient future benefits or strategic value.