Question 30
A public library replacement project has a sponsor and project manager but nobody accountable for specialist delivery capability or the users' acceptance needs. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that pRINCE2 roles separate investment direction, benefit and user interests, and delivery capability so that one stakeholder cannot silently stand for all three. That reasoning makes the targeted action appropriate: establish project board representation for business, user and supplier interests with explicitly agreed accountability and decision rights. The described project conditions show why the distinction matters: A public library replacement project has a sponsor and project manager but nobody accountable for specialist delivery capability or the users' acceptance needs.
Incorrect Answers
Keep work within delegated authority describes a different management issue. The relevant cause instead is that pRINCE2 roles separate investment direction, benefit and user interests, and delivery capability so that one stakeholder cannot silently stand for all three.
Manage by stages for an uncertain rollout describes a different management issue. The relevant cause instead is that pRINCE2 roles separate investment direction, benefit and user interests, and delivery capability so that one stakeholder cannot silently stand for all three.
Separate assurance from delivery describes a different management issue. The relevant cause instead is that pRINCE2 roles separate investment direction, benefit and user interests, and delivery capability so that one stakeholder cannot silently stand for all three.