Question 50
A mobile tax application is forecast to exceed its approved stage cost tolerance even though invoices remain below the limit today; the manager proposes waiting for actual overspend. Why is the proposed way of working inappropriate in this situation?
Explanation
Correct Answer
The important PRINCE2 distinction is that manage by exception delegates daily control within tolerances but requires a forecast breach to reach the authority empowered to reset the constraint. That reasoning makes the targeted action appropriate: escalate the forecast exception promptly to the proper decision authority and prepare an exception report rather than silently consuming unapproved tolerance. The described project conditions show why the distinction matters: A mobile tax application is forecast to exceed its approved stage cost tolerance even though invoices remain below the limit today.
Incorrect Answers
Stop work when benefits no longer support investment describes a different management issue. Here the observed concern is: A mobile tax application is forecast to exceed its approved stage cost tolerance even though invoices remain below the limit today The relevant cause instead is that manage by exception delegates daily control within tolerances but requires a forecast breach to reach the authority empowered to reset the constraint.
Separate assurance from delivery describes a different management issue. The relevant cause instead is that manage by exception delegates daily control within tolerances but requires a forecast breach to reach the authority empowered to reset the constraint.
Clarify the business-user-supplier interests describes a different management issue. The relevant cause instead is that manage by exception delegates daily control within tolerances but requires a forecast breach to reach the authority empowered to reset the constraint.