Question 70
A medical records upgrade has a calendar-based completion date but no agreed criteria demonstrating secure clinical workflow or usable handover products. What underlying management principle most directly explains the concern?
Explanation
Correct Answer
The important PRINCE2 distinction is that a product focus provides a shared basis for scope, quality, planning and acceptance; completion of tasks alone does not prove usable deliverables exist. That reasoning makes the targeted action appropriate: define the required outputs and measurable acceptance and quality criteria before detailed activity scheduling or claiming completion. The described project conditions show why the distinction matters: A medical records upgrade has a calendar-based completion date but no agreed criteria demonstrating secure clinical workflow or usable handover products.
Incorrect Answers
Separate assurance from delivery describes a different management issue. The relevant cause instead is that a product focus provides a shared basis for scope, quality, planning and acceptance; completion of tasks alone does not prove usable deliverables exist.
Use lessons from a prior project describes a different management issue. The relevant cause instead is that a product focus provides a shared basis for scope, quality, planning and acceptance; completion of tasks alone does not prove usable deliverables exist.
Manage by stages for an uncertain rollout describes a different management issue. The relevant cause instead is that a product focus provides a shared basis for scope, quality, planning and acceptance; completion of tasks alone does not prove usable deliverables exist.