Question 80
A multinational regulated deployment wants to remove risk and exception controls because an agile team uses short iterations and dislikes lengthy documents. Which ongoing control would best prevent this failure from recurring?
Explanation
Correct Answer
Review the tailoring approach as complexity, external assurance needs, delivery cadence or project risk changes over time. It is appropriate because tailoring changes how management products and controls are implemented, not whether justification, roles, stages, products and delegated authority matter. The recurring failure risk is illustrated by: A multinational regulated deployment wants to remove risk and exception controls because an agile team uses short iterations and dislikes lengthy documents.
Incorrect Answers
This repeating check is mainly concerned with separate assurance from delivery, not with the recurring weakness described here: A multinational regulated deployment wants to remove risk and exception controls because an agile team uses short iterations and dislikes lengthy documents. The useful ongoing safeguard in this situation is to review the tailoring approach as complexity, external assurance needs, delivery cadence or project risk changes over time.
This repeating check is mainly concerned with stop work when benefits no longer support investment, not with the recurring weakness described here: A multinational regulated deployment wants to remove risk and exception controls because an agile team uses short iterations and dislikes lengthy documents. The useful ongoing safeguard in this situation is to review the tailoring approach as complexity, external assurance needs, delivery cadence or project risk changes over time.
This repeating check is mainly concerned with use lessons from a prior project, not with the recurring weakness described here: A multinational regulated deployment wants to remove risk and exception controls because an agile team uses short iterations and dislikes lengthy documents. The useful ongoing safeguard in this situation is to review the tailoring approach as complexity, external assurance needs, delivery cadence or project risk changes over time.