Question 190
A manufacturing robotics rollout expects faster throughput yet will temporarily disrupt shift coverage and require staff reassignment. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that investment evaluation must acknowledge credible negative effects on stakeholders, because a net case that ignores them can mislead authorization and adoption decisions. That reasoning makes the targeted action appropriate: record material disbenefits and how they will be managed, rather than hiding adverse consequences behind aggregate positive benefit forecasts. The described project conditions show why the distinction matters: A manufacturing robotics rollout expects faster throughput yet will temporarily disrupt shift coverage and require staff reassignment.
Incorrect Answers
Exploit or enhance an opportunity describes a different management issue. The relevant cause instead is that investment evaluation must acknowledge credible negative effects on stakeholders, because a net case that ignores them can mislead authorization and adoption decisions.
Distinguish project board interests describes a different management issue. The relevant cause instead is that investment evaluation must acknowledge credible negative effects on stakeholders, because a net case that ignores them can mislead authorization and adoption decisions.
Assign ownership for realized benefits describes a different management issue. The relevant cause instead is that investment evaluation must acknowledge credible negative effects on stakeholders, because a net case that ignores them can mislead authorization and adoption decisions.