Question 200
A local authority technology project has two senior suppliers making competing assertions about viability but no single owner directing the investment case. Which recurring review would keep this control effective as the project changes?
Explanation
Correct Answer
Define escalation and delegation arrangements that preserve executive accountability even when urgent decisions arise between formal meetings. It is appropriate because the executive owns the business interest in the project and cannot substitute technical supplier enthusiasm or administrative convenience for accountable governance. The recurring failure risk is illustrated by: A local authority technology project has two senior suppliers making competing assertions about viability but no single owner directing the investment case.
Incorrect Answers
This repeating check is mainly concerned with control an off-specification, not with the recurring weakness described here: A local authority technology project has two senior suppliers making competing assertions about viability but no single owner directing the investment case. The useful ongoing safeguard in this situation is to define escalation and delegation arrangements that preserve executive accountability even when urgent decisions arise between formal meetings.
This repeating check is mainly concerned with assign ownership for realized benefits, not with the recurring weakness described here: A local authority technology project has two senior suppliers making competing assertions about viability but no single owner directing the investment case. The useful ongoing safeguard in this situation is to define escalation and delegation arrangements that preserve executive accountability even when urgent decisions arise between formal meetings.
This repeating check is mainly concerned with assess impact before approving a change, not with the recurring weakness described here: A local authority technology project has two senior suppliers making competing assertions about viability but no single owner directing the investment case. The useful ongoing safeguard in this situation is to define escalation and delegation arrangements that preserve executive accountability even when urgent decisions arise between formal meetings.