Question 220
A data-sharing project manager approves an extra stage budget after forecasting a tolerance breach, without consulting the project board. What repeating management check should be included in the project controls?
Explanation
Correct Answer
Document decision authority and escalation thresholds when plans and stages are approved, then use them consistently. It is appropriate because pRINCE2 separates directing the project from managing within delegated tolerances; confusing the two either weakens control or creates avoidable micromanagement. The recurring failure risk is illustrated by: A data-sharing project manager approves an extra stage budget after forecasting a tolerance breach, without consulting the project board.
Incorrect Answers
This repeating check is mainly concerned with project support and administrative control, not with the recurring weakness described here: A data-sharing project manager approves an extra stage budget after forecasting a tolerance breach, without consulting the project board. The useful ongoing safeguard in this situation is to document decision authority and escalation thresholds when plans and stages are approved, then use them consistently.
This repeating check is mainly concerned with team manager work-package accountability, not with the recurring weakness described here: A data-sharing project manager approves an extra stage budget after forecasting a tolerance breach, without consulting the project board. The useful ongoing safeguard in this situation is to document decision authority and escalation thresholds when plans and stages are approved, then use them consistently.
This repeating check is mainly concerned with allocate responsibilities across a hybrid project, not with the recurring weakness described here: A data-sharing project manager approves an extra stage budget after forecasting a tolerance breach, without consulting the project board. The useful ongoing safeguard in this situation is to document decision authority and escalation thresholds when plans and stages are approved, then use them consistently.