Question 230
A civil works subcontractor completes its assigned drainage installation but provides no delivery evidence or formal completion confirmation to the project manager. What underlying management principle most directly explains the concern?
Explanation
Correct Answer
The important PRINCE2 distinction is that a team manager coordinates production of assigned products, while the project manager remains responsible for stage-level oversight and integration. That reasoning makes the targeted action appropriate: agree a work package with the team manager covering products, constraints, tolerances, reports and acceptance, and monitor its authorized delivery. The described project conditions show why the distinction matters: A civil works subcontractor completes its assigned drainage installation but provides no delivery evidence or formal completion confirmation to the project manager.
Incorrect Answers
Separate assurance, control and acceptance describes a different management issue. The relevant cause instead is that a team manager coordinates production of assigned products, while the project manager remains responsible for stage-level oversight and integration.
Compare practical options before commitment describes a different management issue. The relevant cause instead is that a team manager coordinates production of assigned products, while the project manager remains responsible for stage-level oversight and integration.
Use a risk budget for uncertainty describes a different management issue. The relevant cause instead is that a team manager coordinates production of assigned products, while the project manager remains responsible for stage-level oversight and integration.