Question 250
An outsourced citizen portal contracts for milestone dates but says nothing about who can approve changes or accept supplier deliverables. Which diagnosis most accurately explains the gap in control?
Explanation
Correct Answer
The important PRINCE2 distinction is that supplier relationships introduce contractual obligations and incentives that must align with the project management structure and accepted products. That reasoning makes the targeted action appropriate: define contractual interfaces, decision authorities and commercial controls through a suitable commercial management approach and role descriptions. The described project conditions show why the distinction matters: An outsourced citizen portal contracts for milestone dates but says nothing about who can approve changes or accept supplier deliverables.
Incorrect Answers
Independent project assurance describes a different management issue. Here the observed concern is: An outsourced citizen portal contracts for milestone dates but says nothing about who can approve changes or accept supplier deliverables. The relevant cause instead is that supplier relationships introduce contractual obligations and incentives that must align with the project management structure and accepted products.
Project support and administrative control describes a different management issue. The relevant cause instead is that supplier relationships introduce contractual obligations and incentives that must align with the project management structure and accepted products.
Distinguish project board interests describes a different management issue. The relevant cause instead is that supplier relationships introduce contractual obligations and incentives that must align with the project management structure and accepted products.