Question 270
An academic records migration estimates developer hours before agreeing which data sets, reconciliation reports and user interfaces must be accepted. Why is the proposed way of working inappropriate in this situation?
Explanation
Correct Answer
The important PRINCE2 distinction is that product-based planning reduces the risk of completing activities that do not produce what users actually need or can accept. That reasoning makes the targeted action appropriate: use product-based planning to define the required products and their quality needs before deriving activities, dependencies and estimates. The described project conditions show why the distinction matters: An academic records migration estimates developer hours before agreeing which data sets, reconciliation reports and user interfaces must be accepted.
Incorrect Answers
Distinguish owner and actionee describes a different management issue. The relevant cause instead is that product-based planning reduces the risk of completing activities that do not produce what users actually need or can accept.
Allocate responsibilities across a hybrid project describes a different management issue. The relevant cause instead is that product-based planning reduces the risk of completing activities that do not produce what users actually need or can accept.
Assign ownership for realized benefits describes a different management issue. The relevant cause instead is that product-based planning reduces the risk of completing activities that do not produce what users actually need or can accept.