Question 290
A flood-defense programme creates one detailed six-year daily task plan despite uncertainty in later funding and permission stages. Which PRINCE2 reasoning best explains why the current approach is inadequate?
Explanation
Correct Answer
The important PRINCE2 distinction is that pRINCE2 planning has layers because board decisions, stage coordination and team execution require different levels of detail and certainty. That reasoning makes the targeted action appropriate: use a project-level overview, detailed near-term stage planning and appropriate team plans for delegated delivery work. The described project conditions show why the distinction matters: A flood-defense programme creates one detailed six-year daily task plan despite uncertainty in later funding and permission stages.
Incorrect Answers
Tailor planning for iterative delivery describes a different management issue. The relevant cause instead is that pRINCE2 planning has layers because board decisions, stage coordination and team execution require different levels of detail and certainty.
Manage dependencies with a product flow describes a different management issue. The relevant cause instead is that pRINCE2 planning has layers because board decisions, stage coordination and team execution require different levels of detail and certainty.
Choose an exception plan after escalation describes a different management issue. The relevant cause instead is that pRINCE2 planning has layers because board decisions, stage coordination and team execution require different levels of detail and certainty.